| Septic Release Inspection |
|
Health Dept |
3/8/2022 |
| Passed: Building - Footer |
|
Matt Forsyth |
4/27/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/27/2022 |
| Failed: Building - Slab |
Locked Up |
Matt Forsyth |
5/18/2022 |
| Passed: Building - Slab |
|
Matt Forsyth |
5/18/2022 |
| Passed: Building - Lintel/Tie Beam |
|
Matt Forsyth |
6/6/2022 |
| Passed: Building - Masonry Wall Reinforcing |
|
Matt Forsyth |
6/6/2022 |
| Cancelled: Building - Framing |
|
Emaleigh Williams |
6/28/2022 |
| Cancelled: Electrical - 1st Underground Rough–In |
|
Emaleigh Williams |
6/28/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
6/30/2022 |
| Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
6/30/2022 |
| Passed: Building - Insulation |
|
Matt Forsyth |
7/7/2022 |
| Passed: Building - Final |
Need Step Outside Of Man Door |
Matt Forsyth |
9/12/2022 |