Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
|
Troy Crews |
5/12/2022 |
Release to power company |
|
Troy Crews |
5/12/2022 |
Cancelled: Building - Footer |
|
Troy Crews |
9/19/2022 |
Passed: Engineering - Setbacks |
|
Troy Crews |
9/19/2022 |
Passed: Engineering - Spot Check |
|
Troy Crews |
3/9/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/27/2023 |
Passed: Building - Monolithic Slab |
Using Bait System For Termite. |
Troy Crews |
4/4/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
4/4/2023 |
Failed: Building - Masonry Wall Reinforcing |
Need Elevation Letter Prior To Further Inspections |
Troy Crews |
4/21/2023 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
4/21/2023 |
Passed: Building - Roof Decking |
|
Troy Crews |
4/21/2023 |
Passed: Building - Strapping |
|
Troy Crews |
4/21/2023 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
4/21/2023 |
Passed: Building - Framing |
|
Troy Crews |
5/2/2023 |
Passed: Mechanical - Rough In |
|
Troy Crews |
5/2/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
5/2/2023 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
5/2/2023 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
5/22/2023 |
Cancelled: Building - Insulation |
|
Melissa Garber |
5/24/2023 |
Passed: Building - Insulation |
|
Troy Crews |
5/30/2023 |
Failed: Electrical - Permanent Power |
No Ground Block Screws Missing For Panel Cover |
Troy Crews |
8/4/2023 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
8/7/2023 |
Release to power company |
|
Troy Crews |
8/7/2023 |
Failed: Building - Final |
House Locked, Also Need To Contact Brian Scott City Of Lake City Utilities Regarding Removal Of Sewage Cleanout Fittings. |
Troy Crews |
8/28/2023 |
Passed: Building - Final |
|
Troy Crews |
9/15/2023 |