2/1/2021
|
Application pending.
|
2/2/2021
|
Point Review - Printed-Online Application
THE APPLICATION UPLOADED IS BLANK. PLEASE CORRECT.
PLEASE UPLOAD NECESSARY DOCS-- MG
|
2/2/2021
|
Point Review - On Hold-Incomplete
THE APPLICATION UPLOADED IS BLANK. PLEASE CORRECT.
PLEASE UPLOAD NECESSARY DOCS-- MG
|
3/3/2021
|
Point Review - Processing
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
PLEASE UPLOAD NECESSARY DOCS-- MG
|
3/5/2021
|
Zoning Review - Reviewed
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
|
3/9/2021
|
Plan Review - Documents Required
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
|
3/19/2021
|
Plan Review - Reviewed
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
|
3/19/2021
|
Zoning Review - Corrections Needed
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
|
5/25/2021
|
Zoning Review - Corrections Needed
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
MAY 25, 2021 - STILL WAITING ON APPROVED SITE PLAN FOR APPROVAL.
|
2/3/2022
|
Plan Review - Documents Required
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
MAY 25, 2021 - STILL WAITING ON APPROVED SITE PLAN FOR APPROVAL.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
|
2/16/2022
|
Zoning Review - Reviewed
OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, PLEASE CORRECT.
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
MAY 25, 2021 - STILL WAITING ON APPROVED SITE PLAN FOR APPROVAL.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
2/23/2022
|
Zoning Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTUION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
MAY 25, 2021 - STILL WAITING ON APPROVED SITE PLAN FOR APPROVAL.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
2/23/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTUION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
PLANS MUST BE REVISED TO REFLECT 2020 FLORIDA BUILDING CODE
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
MAY 25, 2021 - STILL WAITING ON APPROVED SITE PLAN FOR APPROVAL.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/4/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/4/2022
|
Zoning Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/7/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/7/2022
|
Zoning Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/7/2022
|
Zoning Review - Reviewed
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/10/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
|
3/14/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*MANUAL J CALCS
*ENERGY CODE CALCS
*SIGNED SUB VF FORM
*PRODUCT APPROVAL CODES
*COMMERCIAL CHECKLIST
*ROOF OPTION SELECTED
*ENV HEALTH OR CITY AVAILABILITY LETTER
APPLICATION SUBMITTED FOR PLAN REVIEW WITH THE UNDERSTANDING THAT IT WILL BE PLACED ON HOLD ONCE PLAN REVIEW HAS BEEN COMPLETED, AS TOO MUCH INFO IS MISSING.
SITE PLAN SUBMITTED DOES NOT MATCH APPROVED SITE PLAN (SDP 21 01). THE APPLICANT MUST SUBMIT SUBMIT AND ABID BY THE APPROVED SITE AND DEVELOPMENT PLAN.
NEED SEALED STRUCTURAL PLANS, ALSO NEED SEALED METAL BUILDING PLANS 2-3-22
SITE PLAN APPROVED BY THE PLANNING & ZONING BOARD ON JANUARY 27, 2022. SEE SDP 21 12 COMPLETE
PLANS IN FILE ARE 2020 IBC NEED 2020 FBC ALSO NEED STEEL BUILDING PLANS
|
3/15/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
pRODUCT APPROVAL CODES-- BLANK UPLOADED
*COMMERCIAL CHECKLIST
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/17/2022
|
Plan Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*SIGNED SUB VF FORM
*COMMERCIAL CHECKLIST
*ENV HEALTH OR CITY AVAILABILITY LETTER
PRODUCT APPROVAL FORM FILLED OUT
|
3/18/2022
|
Plan Review - Plumbing Approved
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/18/2022
|
Plan Review - Mechanical Approved
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/18/2022
|
Plan Review - Electrical Approved
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/18/2022
|
Plan Review - Building Approved
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/18/2022
|
Plan Review - Reviewed
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/18/2022
|
Point Review - Documents Required
*OWNER AND CONTRACTOR SIGNATURE PAGE MUST BE SIGNED BY A CORPORATE OFFICER, AS WELL AS THE CONTRACTOR PLEASE CORRECT.
*ENV HEALTH OR CITY AVAILABILITY LETTER
|
3/24/2022
|
Point Review - Reviewed
NEED CORPORATE CONFIRMATION OF DEAN LAMBERT AS OFFICER
|
3/24/2022
|
Final Review - Documents Required
NEED CORPORATE CONFIRMATION OF DEAN LAMBERT AS OFFICER
|
3/25/2022
|
Final Review - Documents Required
CARTER TO COMPLETE REGISTRATION
|
3/29/2022
|
Final Review - Reviewed
|
3/29/2022
|
Final Review - Payment Needed
|
3/29/2022
|
Permit Issued
Permit #000044032 created and approved.
|
7/19/2022
|
Final Review - Payment Needed
|