| Passed: Building - Footer |
|
Troy Crews |
3/22/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
3/22/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
4/6/2022 |
| Passed: Building - Slab |
|
Troy Crews |
4/12/2022 |
| Passed: Building - Roof Decking |
|
Troy Crews |
5/13/2022 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
5/13/2022 |
| Passed: Building - Framing |
|
Troy Crews |
7/20/2022 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
7/20/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
7/20/2022 |
| Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
7/20/2022 |
| Passed: Building - Insulation |
|
Troy Crews |
8/4/2022 |
| Passed: Electrical - Permanent Power |
Need Septic Final
received 9.30.22 |
Troy Crews |
9/29/2022 |
| Release to power company |
Received Eh 9.30.22 |
Troy Crews |
9/30/2022 |
| Septic Release Inspection |
|
Health Dept |
10/4/2022 |
| Certificate-Release Certificate |
Assesments Paid |
Troy Crews |
10/2/2023 |
| (Requested) Building-Final |
|
|
|