Inspection |
Notes |
Performed By |
Date |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Water Test Failed No Water In Riser |
Matt Forsyth |
2/23/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Item Addressed |
Matt Forsyth |
3/2/2022 |
Passed: Building - Monolithic Slab |
|
Matt Forsyth |
3/9/2022 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
3/9/2022 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
3/9/2022 |
Release to power company |
|
Matt Forsyth |
3/9/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
Nail Off Only No Ext. Strapping Done |
Matt Forsyth |
5/13/2022 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
5/16/2022 |
Failed: Building - Slab |
Need Framing And All Ext Strapping Inspections |
Matt Forsyth |
5/26/2022 |
Failed: Building - Framing |
Garage Opening Not Framed Properly (king Studs) Windows Need To Be Tempered Glass |
Matt Forsyth |
7/5/2022 |
Cancelled: Electrical - 2nd Rough-In |
Duplicate- Called Jennifer She Confirmed They Needed Them On 7-8 |
Emaleigh Williams |
7/6/2022 |
Cancelled: Mechanical - Rough In |
Duplicate- Called Jennifer She Confirmed They Needed Them On 7-8 |
Emaleigh Williams |
7/6/2022 |
Cancelled: Plumbing/Gas - Tub Set/Shower Pan |
Duplicate - Called Jennifer She Confirmed They Needed Them On 7-8 |
Emaleigh Williams |
7/6/2022 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
7/8/2022 |
Failed: Mechanical - Rough In |
Exhaust Mate
|
Matt Forsyth |
7/8/2022 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
7/8/2022 |
Passed: Building - Framing |
|
Matt Forsyth |
7/11/2022 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
7/13/2022 |
Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
7/14/2022 |
Passed: Electrical - Permanent Power |
Need Septic Release For Power |
Matt Forsyth |
8/26/2022 |
Release to power company |
|
Melissa Garber |
9/6/2022 |
Septic Release Inspection |
|
Health Dept |
9/6/2022 |
Passed: Building - Final |
|
Matt Forsyth |
9/26/2022 |