Permit Details

Permit Search

Permit

Additions

388 SE ENTERPRISE CT
LAKE CITY, FL 32025

Permit #
000043690
Application #
53462
Status Completed
  1. Submitted Feb 10, 2022
  2. Issued Feb 11, 2022
  3. Expires Jun 5, 2023
  4. Completed Dec 7, 2022

Property

Parcel #
07479-151
Owner
Carlisle Construction
Acres
21.85
Subdivision
—
Zoning
I
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0315C
Description of addition:
Silo and canopy foundation
Select driveway access to property:
Existing Drive
Fire sprinklers?
No
Stories
1
Heated Area (Sqft)
0
Total Area (Sqft)
4500
Total Estimated Cost
175000
Building Height
22
Building Code Construction Type
III
Building Code Element
B
Building Code Occupancy Types
Factory
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Is this an addition for commercial or residential use?
Commercial
Sealed roof decking options. (Must select one.)
N/A
Sealed roof decking explanation for other option.
metal roofing open structure
Service Amps
3500

Status & Review History

  1. Application pending.
  2. City of Lake City
  3. Plan Review - Building Approved
  4. Plan Review - Reviewed
  5. Zoning Review - Reviewed
  6. Final Review - Reviewed
  7. Final Review - Payment Needed
  8. Permit Issued
  9. Final Review - Payment Needed

Contractors

  • Harold Richardson

    W.w. Gay Mechanical Contractors,inc.

    License
    CGC1504951
    Title
    Cert General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Feb 11, 2022

    Passed: Building - Footer

    Foundation Pad For Silo

    Inspected by Troy Crews

  2. Feb 11, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Feb 22, 2022

    Passed: Building - Footer

    Inspected by Troy Crews

  4. Feb 22, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Feb 23, 2022

    Cancelled: Building - Footer

    Inspected by Melissa Garber

  6. Feb 23, 2022

    Cancelled: Engineering - Setbacks

    Inspected by Melissa Garber

  7. May 11, 2022

    Passed: Building - Slab

    South Half

    Inspected by Troy Crews

  8. May 24, 2022

    Passed: Building - Slab

    South End Second Half Of Slab

    Inspected by Troy Crews

  9. Dec 7, 2022

    Passed: Building - Final

    Inspected by Troy Crews