Permit Details

Permit Search

Permit

New Residential Construction

251 SE OAK RIDGE CT
HIGH SPRINGS, FL 32643

Permit #
000043665
Application #
53037
Status Permit Issued This permit expired on Jul 4, 2023.
  1. Submitted Jan 7, 2022
  2. Issued Feb 7, 2022
  3. Expires Jul 4, 2023
  4. Completed —

Property

Parcel #
09969-014
Owner
Hewett Donna S Revocable Trust
Acres
5.16
Subdivision
Oak Ridge Forest
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Permit Issued
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0513C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
792
Total Area (Sqft)
2160
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
22-0064
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.

Status & Review History

  1. Plan Review - Corrections Needed
  2. Point Review - Received-Hard Copy Application
  3. Point Review - Reviewed
  4. Plan Review - Reviewed
  5. Zoning Review - Reviewed
  6. Final Review - Documents Required
  7. Final Review - Documents Required
  8. Final Review - Reviewed
  9. Final Review - Payment Needed
  10. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Mar 7, 2022

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Mar 7, 2022

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Mar 22, 2022

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  4. Mar 22, 2022

    Release to power company

    Inspected by Anthony Aslan

  5. Mar 22, 2022

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Anthony Aslan

  6. Mar 22, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  7. Apr 1, 2022

    Septic Release Inspection

    Inspected by Health Dept

  8. May 17, 2022

    Passed: Building - Framing

    Inspected by Anthony Aslan

  9. Jul 25, 2022

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  10. Jul 25, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  11. Aug 8, 2022

    Passed: Building - Insulation

    All Spray Foam

    Inspected by Anthony Aslan

  12. Jan 5, 2023

    Passed: Building - Final

    Need Final Termite

    Inspected by Anthony Aslan

Documents