Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
1/13/2022 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
1/13/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
1/28/2022 |
Passed: Building - Slab |
Fiber Mesh Concrete |
Matt Forsyth |
2/1/2022 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
2/10/2022 |
Release to power company |
|
Matt Forsyth |
2/10/2022 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
3/18/2022 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
4/18/2022 |
Passed: Building - Wall Sheathing |
Windstorm Osb |
Matt Forsyth |
4/18/2022 |
Passed: Building - Framing |
|
Matt Forsyth |
5/19/2022 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
5/19/2022 |
Failed: Mechanical - Rough In |
Need 3inch Clearance Around Ductwork In Ahu Closet |
Matt Forsyth |
5/19/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
Need Water Test On Tubs |
Matt Forsyth |
5/19/2022 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
5/25/2022 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Tub Water Tested |
Matt Forsyth |
5/25/2022 |
Passed: Building - Insulation |
Need To Get Doors In Asap, Or Cover Openings Temporary. |
Troy Crews |
6/6/2022 |
Passed: Electrical - Permanent Power |
Need Septic |
Matt Forsyth |
10/24/2022 |
Release to power company |
|
Melissa Garber |
10/27/2022 |
Septic Release Inspection |
|
Health Dept |
10/27/2022 |
Failed: Building - Final |
Kitchen Countertops Require Two Branch Circuits For Receptacles Need Blower Door Test Dining Room Sliding Door Not Locking |
Matt Forsyth |
11/17/2022 |
Passed: Building - Final |
|
Troy Crews |
11/21/2022 |