Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Need Compaction Test-rec'd 12.9.21 |
Matt Forsyth |
12/8/2021 |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
12/9/2021 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
12/13/2021 |
Release to power company |
|
Troy Crews |
12/13/2021 |
Passed: Building - Monolithic Slab |
|
Matt Forsyth |
12/14/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
12/14/2021 |
Passed: Building - Roof Decking |
|
Troy Crews |
2/10/2022 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
2/10/2022 |
Passed: Building - Framing |
|
Troy Crews |
3/1/2022 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
3/1/2022 |
Failed: Mechanical - Rough In |
Main Return Not Complete, Need Nail Plate At Dryer Duct. |
Troy Crews |
3/1/2022 |
Failed: Plumbing/Gas - 2nd Rough-In |
No Pressure On Water Lines |
Troy Crews |
3/1/2022 |
Failed: Building - Insulation |
Mechanical And Plumbing Not Passed Yet |
Troy Crews |
3/4/2022 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
4/29/2022 |
Failed: Electrical - Permanent Power |
Need Culvert Final, Need Septic Final, Need Insulation Certification Letter From Insulation Contractor Certifying Insulation Since It Was Not Inspected. |
Troy Crews |
4/29/2022 |
Passed: Electrical - Permanent Power |
Need Septic Final |
Troy Crews |
5/3/2022 |
Release to power company |
|
Troy Crews |
5/3/2022 |
Passed: Building - Insulation |
Letter On File |
Troy Crews |
5/3/2022 |
Passed: Mechanical - Rough In |
Items |
Troy Crews |
5/3/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
5/3/2022 |
Septic Release Inspection |
|
Health Dept |
5/4/2022 |
Failed: Building - Final |
Need Blower Door Test, Water Heater Wired In, Disconnect On Power Supply At Air Handler. |
Troy Crews |
5/24/2022 |
Passed: Building - Final |
Items Corrected, Blower Door Received |
Troy Crews |
5/25/2022 |