Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Passed By Mmcelroy--private Provider |
Private Provider |
2/7/2022 |
Passed: Building - Monolithic Slab |
Passed By Sthomas-- Private Provider |
Private Provider |
2/18/2022 |
Passed: Engineering - Setbacks |
Passed By Sthomas-- Private Provider |
Private Provider |
2/18/2022 |
Passed: Building - Roof Decking |
Passed By Sthomas |
Private Provider |
3/24/2022 |
Passed: Building - Wall Sheathing |
Passed By Sthomas |
Private Provider |
3/24/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
Window Attachment And Flashing-- Passed By Sthomas |
Private Provider |
4/11/2022 |
Passed: Building - Framing |
Passed By Tmccarthy |
Private Provider |
4/14/2022 |
Passed: Building - Roof Decking |
Passed By Tmccarthy |
Private Provider |
4/14/2022 |
Passed: Electrical - 2nd Rough-In |
Passed By Tmccarthy |
Private Provider |
4/14/2022 |
Failed: Mechanical - Rough In |
Incomplete By Tmccarthy- Rescheduled |
Private Provider |
4/14/2022 |
Failed: Plumbing/Gas - 2nd Rough-In |
Incomplete By Tmccarthy-- Rescheduled |
Private Provider |
4/14/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
Passed By Tmccarthy |
Private Provider |
4/20/2022 |
Passed: Mechanical - Rough In |
Partial Inspection By Tmccarthy |
Private Provider |
4/20/2022 |
Passed: Building - Insulation |
Passed By Sthomas |
Private Provider |
4/22/2022 |
Passed: Building - Wall Sheathing |
Drywall Attachment - Passed By Sthomas |
Private Provider |
4/29/2022 |
Passed: Electrical - Permanent Power |
Passed By Tmccarthy |
Private Provider |
6/29/2022 |
Release to power company |
|
Private Provider |
6/30/2022 |
Passed: Building - Final |
Passed By Mmcelroy |
Private Provider |
7/13/2022 |