Permit Details

Permit Search

Permit

New Residential Construction

567 SE GILES MARTIN AVE
LAKE CITY, FL 32024

Permit #
000043185
Application #
52109
Status Completed
  1. Submitted Oct 13, 2021
  2. Issued Nov 16, 2021
  3. Expires Feb 21, 2023
  4. Completed Aug 29, 2022

Property

Parcel #
09767-001
Owner
Chastain Andrew Jackson & Brittany
Acres
10.03
Subdivision
Means Unr
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0505C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2225
Total Area (Sqft)
3554
Building Height
20
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0910
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Point Review - Printed-Online Application
  3. Point Review - Reviewed
  4. Plan Review - Building Approved
  5. Plan Review - Electrical Approved
  6. Plan Review - Mechanical Approved
  7. Plan Review - Plumbing Approved
  8. Plan Review - Reviewed
  9. Zoning Review - Reviewed
  10. Zoning Review - Reviewed
  11. Final Review - Documents Required
  12. Final Review - Documents Required
  13. Final Review - Payment Needed
  14. Permit Issued
  15. Final Review - Payment Needed

Contractors

  • Joel G Buzbee

    G Buzbee, Inc

    License
    CGC061980
    Title
    Cert General
    Role
    Contractor

    County License & State License Expired.

  • Paul K Coleman

    Colemans Plumbing Inc.

    License
    CFC1425624
    Title
    Certified Plumbing
    Role
    Subcontractor

    County License & State License & Employees Workers Comp Expired.

  • Chad White

    Ck Electric Llc

    License
    EC13002222
    Title
    Electrical Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • Donald R Davis

    High Springs Electric Inc

    License
    CAC1815367
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Jan 6, 2022

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  2. Jan 6, 2022

    Passed: Building - Footer

    Inspected by Anthony Aslan

  3. Jan 14, 2022

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  4. Jan 14, 2022

    Release to power company

    Inspected by Anthony Aslan

  5. Feb 2, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  6. Feb 15, 2022

    Passed: Building - Slab

    Inspected by Anthony Aslan

  7. Feb 28, 2022

    Passed: Building - Wall Sheathing

    Inspected by Anthony Aslan

  8. Feb 28, 2022

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  9. Mar 3, 2022

    Passed: Building - Framing

    Inspected by Anthony Aslan

  10. Mar 24, 2022

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  11. Mar 24, 2022

    Failed: Plumbing/Gas - 2nd Rough-In

    No Pressure On Gas, Plumbing Vent On Master Side Not Strapped Not Pitching Draining Back

    Inspected by Anthony Aslan

  12. Mar 24, 2022

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Anthony Aslan

  13. Mar 24, 2022

    Passed: Mechanical - Rough In

    Gasket On Pantry Boot, No Screws In Kitchen Exhaust Pipe Joints, Dryer Through Bearing Wall Exceeds 40-60% Notch Or Drilling

    Inspected by Anthony Aslan

  14. Mar 31, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  15. Mar 31, 2022

    Passed: Building - Insulation

    Inspected by Anthony Aslan

  16. May 25, 2022

    Septic Release Inspection

    Inspected by Health Dept

  17. Jun 3, 2022

    Passed: Electrical - Permanent Power

    Inspected by Anthony Aslan

  18. Jun 3, 2022

    Release to power company

    Inspected by Anthony Aslan

  19. Aug 25, 2022

    Passed: Building - Final

    Need Anchors On A/c Condenser, Gfic In Soffit Need Outdoor Covers. Ones Under Porches Need To Be Weather Resistant Outlets.

    Inspected by Anthony Aslan

  20. Aug 29, 2022

    Certificate-Release Certificate

    Correction Made

    Inspected by Anthony Aslan

Documents