Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 313 SW CROSS POINTE CT
LAKE CITY, FL 32024
Parcel #: 03051-120
Acres: 5.00
Owner: Spence William P Jr & Jessica
Subdivision: South Pointe
Zoning: RR
Flood Zone: X
District: 3
Application #: 50456
Permit #: 000043028
Related Permit:
Submitted: Tuesday, September 28, 2021
Issued: Monday, October 25, 2021
Expires: Friday, August 12, 2022
Completed: Friday, August 12, 2022
Status: Completed
Septic Release? Yes
Notes:

Job Details
Elevation regulation Minimum Requirement
Finished floor requirement One foot above the road
Fema map number 12023C0290D
In floodway N
This is the construction of a Single Family Dwelling
Setbacks Front 25'
Setback Side 1 10'
Setback Side 2 10'
Setbacks Rear 15'
Stories 1
Heated Area (Sqft) 2250
Total Area (Sqft) 3348
Building Height 21
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000) 21-0866
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Review Notes
9/2/2021 Application pending.
9/28/2021 Point Review - Printed-Online Application
9/28/2021 Point Review - Reviewed
10/4/2021 Zoning Review - Reviewed
10/7/2021 Plan Review - Building Approved
10/7/2021 Plan Review - Electrical Approved
10/7/2021 Plan Review - Mechanical Approved
10/7/2021 Plan Review - Plumbing Approved
10/7/2021 Plan Review - Reviewed
10/7/2021 Zoning Review - Reviewed
10/7/2021 Final Review - Documents Required
10/22/2021 Final Review - Documents Required
10/25/2021 Final Review - Payment Needed
10/25/2021 Permit Issued
7/19/2022 Final Review - Payment Needed
Contractors
Name/ Business License Title Role
Isaiah Cully
Ic Construction Llc
CBC1259655 Building Contractor Contractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Tyler M Turner
Tmt Roofing Llc
CCC1330410 Cert Roofing Subcontractor
Everton D Ruddock
D&s Lighting Inc
EC13003800 Electrical Contractor Subcontractor
Clinton G Wilson
Wilson Heat & Air Inc
CAC057886 Class B A/c Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Troy Crews 11/4/2021
Passed: Engineering - Setbacks Troy Crews 11/4/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 12/17/2021
Passed: Building - Slab Need 6 Inch Wall At Shower Matt Forsyth 12/28/2021
Passed: Building - Wall Sheathing Matt Forsyth 1/25/2022
Passed: Building - Roof Decking Matt Forsyth 2/25/2022
Passed: Building - Wall Sheathing Matt Forsyth 2/25/2022
Passed: Building - Framing Missing Garage Portal Hold Down(1) Matt Forsyth 3/8/2022
Septic Release Inspection Health Dept 4/1/2022
Passed: Electrical - 2nd Rough-In Matt Forsyth 4/5/2022
Passed: Mechanical - Rough In Matt Forsyth 4/5/2022
Passed: Plumbing/Gas - 2nd Rough-In Bathtub Leaking At Rubber Washer Vent Stack Cut In Attic Matt Forsyth 4/5/2022
Passed: Building - Insulation Matt Forsyth 4/26/2022
Passed: Electrical - Permanent Power Troy Crews 7/20/2022
Release to power company Troy Crews 7/20/2022
Rescheduled 8/3/2022:Building - Final Matt Forsyth 8/1/2022
Rescheduled 8/4/2022:Building - Final Matt Forsyth 8/3/2022
Failed: Building - Final Plug For Kitchen Hood Needs To Be Clamped Over Sheath Wires Exposed, Oven Duct Needs Extension And Grill In Soffit, Fresh Air Outlet In Soffit Needs Grill, One Register Cover Missing Inside. One Window Not Opening Properly. Troy Crews 8/4/2022
Rescheduled 8/12/2022:Building - Final Matt Forsyth 8/11/2022
Passed: Building - Final Matt Forsyth 8/12/2022
Documents
File Name Date File Size