Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 225 SW PINEHURST DR
LAKE CITY, FL 32024
Parcel #: 03087-104
Acres: 0.71
Owner: Entrust Holdings Llc
Subdivision: Forest Country Sixth Addition
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 51558
Permit #: 000043010
Related Permit: Culvert: 000043011
Submitted: Wednesday, October 13, 2021
Issued: Friday, October 22, 2021
Expires: Tuesday, May 2, 2023
Completed: Tuesday, May 2, 2023
Status: Completed
Septic Release? Yes
Notes:
ELEVATION CONFIRMATION REC'D @ 104.2'
Job Details
Elevation regulation Subdivision Plat
Finished floor requirement 103.4'
Requirement needed By Nailing Inspection
Document needed is a Surveyor letter giving the Finished Floor Elevation
Document receieved Yes
Fema map number 12023C0289D
In floodway N
This is the construction of a Single Family Dwelling
Setbacks Front 25
Setback Side 1 10
Setback Side 2 10
Setbacks Rear 15
Stories 1
Heated Area (Sqft) 2499
Total Area (Sqft) 3300
Building Height 21
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000) 21-0762
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Review Notes
9/14/2021 Point Review - Received-Hard Copy Application
9/22/2021 Zoning Review - Reviewed
9/28/2021 Plan Review - Documents Required
10/5/2021 Plan Review - Documents Required
10/11/2021 Plan Review - Plumbing Approved
10/11/2021 Plan Review - Mechanical Approved
10/11/2021 Plan Review - Electrical Approved
10/11/2021 Plan Review - Building Approved
10/11/2021 Plan Review - Reviewed
10/12/2021 Zoning Review - Reviewed
10/15/2021 Final Review - Documents Required
10/22/2021 Permit Issued
1/5/2023 Final Review - Payment Needed
Contractors
Name/ Business License Title Role
Frank A Todd Iii(mike)
Mike Todd Construction Inc
CGC006209 General Contractor Contractor
Marcus Matthews
Matthews Electric Llc
EC13005459 Electrical Contractor Subcontractor
Don C Bills Sr
Hometown Plumbing Services Llc
CFC1428890 Plumbing Contractor Subcontractor
Derrick L Williams
Dl Williams Heating & Cooling Llc
CAC1816913 Class "b" A/c Contractor Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Jones, Richard 10/25/2021
Cancelled: Building - Footer Troy Crews 1/19/2022
Cancelled: Engineering - Setbacks Troy Crews 1/19/2022
Cancelled: Electrical - Temporary Service Troy Crews 1/19/2022
Passed: Building - Footer Matt Forsyth 1/20/2022
Passed: Engineering - Setbacks Matt Forsyth 1/20/2022
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 3/2/2022
Passed: Building - Slab Fibermesh Concrete Matt Forsyth 3/9/2022
Passed: Building - Masonry Wall Reinforcing This Inspection Was For Ext Walls Contractor Working To Get Elevation Certificate Matt Forsyth 7/5/2022
Passed: Electrical - 1st Underground Rough–In Inspection Was For Second Rough Electric Matt Forsyth 8/25/2022
Passed: Plumbing/Gas - 2nd Rough-In Matt Forsyth 8/25/2022
Passed: Building - Insulation Need Mechanical Before Cover Up Matt Forsyth 9/1/2022
Failed: Mechanical - Rough In This Project Is Missing Several Inspections Wall Sheathing Roof Sheathing Framing Inspection Those Need To Be Completed Before Moving Forward On Any Work Other Than Completing These Inspections Matt Forsyth 9/22/2022
Cancelled: Building - Wall Sheathing Matt Forsyth 9/26/2022
Cancelled: Electrical - 2nd Rough-In Matt Forsyth 9/26/2022
Passed: Building - Strapping Matt Forsyth 9/26/2022
Passed: Building - Framing Matt Forsyth 9/26/2022
Passed: Building - Roof Decking Matt Forsyth 9/26/2022
Cancelled: Plumbing/Gas - 2nd Rough-In Matt Forsyth 9/26/2022
Passed: Mechanical - Rough In Matt Forsyth 9/26/2022
Cancelled: Electrical - Permanent Power Matt Forsyth 1/6/2023
Passed: Electrical - Permanent Power Need And Septic And Driveway Matt Forsyth 1/9/2023
Septic Release Inspection Health Dept 2/20/2023
Release to power company Melissa Garber 2/23/2023
Passed: Engineering - Final Driveway Smith, Blake 2/23/2023
Release to power company Melissa Garber 3/2/2023
Passed: Building - Final Need Bdt And Final Termite Matt Forsyth 4/11/2023
Certificate-Release Certificate Matt Forsyth 5/2/2023