| Inspection |
Notes |
Performed By |
Date |
| Passed: Engineering - Initial Driveway |
|
Jones, Richard |
10/25/2021 |
| Cancelled: Building - Footer |
|
Troy Crews |
1/19/2022 |
| Cancelled: Engineering - Setbacks |
|
Troy Crews |
1/19/2022 |
| Cancelled: Electrical - Temporary Service |
|
Troy Crews |
1/19/2022 |
| Passed: Building - Footer |
|
Matt Forsyth |
1/20/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
1/20/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
3/2/2022 |
| Passed: Building - Slab |
Fibermesh Concrete |
Matt Forsyth |
3/9/2022 |
| Passed: Building - Masonry Wall Reinforcing |
This Inspection Was For Ext Walls Contractor Working To Get Elevation Certificate |
Matt Forsyth |
7/5/2022 |
| Passed: Electrical - 1st Underground Rough–In |
Inspection Was For Second Rough Electric |
Matt Forsyth |
8/25/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
8/25/2022 |
| Passed: Building - Insulation |
Need Mechanical Before Cover Up |
Matt Forsyth |
9/1/2022 |
| Failed: Mechanical - Rough In |
This Project Is Missing Several Inspections Wall Sheathing Roof Sheathing Framing Inspection Those Need To Be Completed Before Moving Forward On Any Work Other Than Completing These Inspections |
Matt Forsyth |
9/22/2022 |
| Cancelled: Building - Wall Sheathing |
|
Matt Forsyth |
9/26/2022 |
| Cancelled: Electrical - 2nd Rough-In |
|
Matt Forsyth |
9/26/2022 |
| Passed: Building - Strapping |
|
Matt Forsyth |
9/26/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
9/26/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
9/26/2022 |
| Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
9/26/2022 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
9/26/2022 |
| Cancelled: Electrical - Permanent Power |
|
Matt Forsyth |
1/6/2023 |
| Passed: Electrical - Permanent Power |
Need And Septic And Driveway |
Matt Forsyth |
1/9/2023 |
| Septic Release Inspection |
|
Health Dept |
2/20/2023 |
| Release to power company |
|
Melissa Garber |
2/23/2023 |
| Passed: Engineering - Final Driveway |
|
Smith, Blake |
2/23/2023 |
| Release to power company |
|
Melissa Garber |
3/2/2023 |
| Passed: Building - Final |
Need Bdt And Final Termite |
Matt Forsyth |
4/11/2023 |
| Certificate-Release Certificate |
|
Matt Forsyth |
5/2/2023 |