8/23/2021
|
Application pending.
|
10/1/2021
|
Point Review - Printed-Online Application
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/1/2021
|
Point Review - Reviewed
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/4/2021
|
Zoning Review - Reviewed
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/5/2021
|
Plan Review - Building Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
*NEED ONE HARD COPY OF RAISED SEAL
|
10/5/2021
|
Plan Review - Electrical Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
*NEED ONE HARD COPY OF RAISED SEAL
|
10/5/2021
|
Plan Review - Mechanical Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
*NEED ONE HARD COPY OF RAISED SEAL
|
10/5/2021
|
Plan Review - Plumbing Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
*NEED ONE HARD COPY OF RAISED SEAL
|
10/5/2021
|
Plan Review - Documents Required
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
*NEED ONE HARD COPY OF RAISED SEAL
|
10/11/2021
|
Plan Review - Building Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/11/2021
|
Plan Review - Electrical Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/11/2021
|
Plan Review - Mechanical Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/11/2021
|
Plan Review - Plumbing Approved
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/11/2021
|
Plan Review - Reviewed
NEEDED:
*ARCHITECTURAL & SEALED STRUCTURAL PLANS-- MAY NEED HARD COPY SINCE CRIMP SEALED-- TROY WILL DETERMINE UPON REVIEW
|
10/13/2021
|
Zoning Review - Reviewed
|
10/13/2021
|
Final Review - Reviewed
|
10/13/2021
|
Final Review - Payment Needed
|
10/20/2021
|
Permit Issued
Permit #000042989 created and approved.
|
8/22/2022
|
Final Review - Payment Needed
|