| Inspection |
Notes |
Performed By |
Date |
| Passed: Fire - Plan Review |
|
Jeff Crawford |
7/21/2021 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
10/15/2021 |
| Release to power company |
|
Troy Crews |
10/15/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
10/25/2021 |
| Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
10/25/2021 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
10/29/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
10/29/2021 |
| Passed: Building - Roof Decking |
|
Troy Crews |
11/16/2021 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
11/16/2021 |
| Passed: Fire - Light Test |
Inspected 11/17/21. Passed. |
Jeff Crawford |
11/17/2021 |
| Passed: Building - Framing |
|
Troy Crews |
11/18/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
11/24/2021 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
11/24/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Pressure Test Before Insulation |
Troy Crews |
11/24/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
11/30/2021 |
| Passed: Electrical - Permanent Power |
Need D.o.t. Approval Prior To C.o. And Asesment Fees Paid. |
Troy Crews |
12/21/2021 |
| Passed: Building - Above Ceiling |
|
Troy Crews |
12/21/2021 |
| Release to power company |
|
Troy Crews |
12/22/2021 |
| Passed: Building - Final |
All Inspections Done Final C.o. To Be Released Upon Final D.o.t. Inspection Building Ready For Occupancy. |
Troy Crews |
12/30/2021 |
| Passed: Fire - Fire Final |
Identification Labels Secured To Be Suppression Pull Stations, 3 Extinguishers Still To Be Mounted, All Of Which Are On Site |
Lance Hill |
12/30/2021 |
| Passed: Building - Final |
|
Troy Crews |
1/27/2022 |