Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Jones, Richard |
10/6/2021 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
10/27/2021 |
Failed: Building - Footer |
Need Compaction Test |
Anthony Aslan |
10/27/2021 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
10/27/2021 |
Passed: Building - Footer |
Rec'd Compaction Test |
Anthony Aslan |
10/27/2021 |
Passed: Building - Footer |
Already Done Need Compaction |
Troy Crews |
11/3/2021 |
Passed: Engineering - Setbacks |
|
Troy Crews |
11/3/2021 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
11/10/2021 |
Release to power company |
|
Troy Crews |
11/10/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
11/24/2021 |
Cancelled: Building - Slab |
|
Melissa Garber |
11/29/2021 |
Passed: Building - Slab |
|
Anthony Aslan |
12/1/2021 |
Failed: Building - Framing |
More Than 50% Bearing Top Plate Notched Or Drill Requires Reinforcement |
Anthony Aslan |
1/11/2022 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
1/20/2022 |
Passed: Mechanical - Rough In |
|
Anthony Aslan |
1/20/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
Tub Filled With Water |
Anthony Aslan |
1/20/2022 |
Cancelled: Building - Framing |
|
Anthony Aslan |
1/20/2022 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
1/24/2022 |
Cancelled: Mechanical - Rough In |
|
Anthony Aslan |
1/24/2022 |
Cancelled: Electrical - 2nd Rough-In |
|
Anthony Aslan |
1/24/2022 |
Cancelled: Building - Framing |
|
Anthony Aslan |
1/24/2022 |
Passed: Building - Framing |
Rec Engineer Letter |
Anthony Aslan |
1/25/2022 |
Passed: Building - Insulation |
Window In Kitchen Missing Foam Top Of Window |
Anthony Aslan |
1/27/2022 |
Failed: Electrical - Permanent Power |
Panel Cover Not Installed, Outlet Covers In Garage Not Installed
need Septic Release And Drive Release |
Anthony Aslan |
4/13/2022 |
Passed: Electrical - Permanent Power |
Need Septic & Driveway Release |
Anthony Aslan |
4/18/2022 |
Cancelled: Building - Framing |
|
Anthony Aslan |
4/25/2022 |
Cancelled: Electrical - 2nd Rough-In |
|
Anthony Aslan |
4/25/2022 |
Cancelled: Mechanical - Rough In |
|
Anthony Aslan |
4/25/2022 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/25/2022 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
5/3/2022 |
Release to power company |
|
Melissa Garber |
5/5/2022 |
Septic Release Inspection |
|
Health Dept |
5/5/2022 |
Cancelled: Building - Final |
|
Melissa Garber |
5/26/2022 |
Passed: Building - Final |
Lock Out On Breaker For Well (rec'd Picture) |
Anthony Aslan |
5/27/2022 |