Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
10/1/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Will Need Compaction Test For Slab And Footing |
Matt Forsyth |
11/18/2021 |
Failed: Building - Footer |
No Compaction Test |
Matt Forsyth |
11/23/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
11/23/2021 |
Passed: Building - Footer |
|
Matt Forsyth |
12/2/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
12/2/2021 |
Failed: Building - Ext Strapping/Wall Sheathing |
Nail Off Inspection Is Before Housewrap Cut Was Made In Wrap Several Places Need To Be Renailed No Gable End Strapping Was Done |
Matt Forsyth |
1/20/2022 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
1/20/2022 |
Failed: Building - Ext Strapping/Wall Sheathing |
Need Strapping On Posts On Porch At Top |
Matt Forsyth |
1/27/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
Item Addressed |
Matt Forsyth |
2/7/2022 |
Passed: Electrical - 1st Underground Rough–In |
This Inspection Was For The Underground Piping To The Electrical Transformer Pole |
Matt Forsyth |
2/7/2022 |
Passed: Mechanical - Rough In |
Need More Landing |
Matt Forsyth |
4/28/2022 |
Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
4/28/2022 |
Passed: Building - Framing |
|
Matt Forsyth |
4/28/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
Tub Water Tested |
Matt Forsyth |
4/28/2022 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/28/2022 |
Passed: Building - Insulation |
|
Matt Forsyth |
5/4/2022 |
Septic Release Inspection |
|
Health Dept |
6/21/2022 |
Passed: Electrical - Permanent Power |
Need Driveway Released |
Matt Forsyth |
6/22/2022 |
Failed: Building - Final |
Power Has Not Been Released Need Driveway Inspection |
Matt Forsyth |
6/28/2022 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
6/29/2022 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
7/1/2022 |
Release to power company |
|
Matt Forsyth |
7/1/2022 |
Passed: Building - Final |
Need Blower Door Test And Final Termite Certificate For Release Of Co-- Rec'd |
Troy Crews |
7/18/2022 |
Certificate-Release Certificate |
|
Troy Crews |
7/20/2022 |