Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Ground Wire Installed |
Matt Forsyth |
9/30/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
9/30/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
11/10/2021 |
Passed: Building - Slab |
|
Troy Crews |
11/17/2021 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
1/3/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
1/3/2022 |
Failed: Building - Framing |
Need Two Straps On Each Side Of Garage Door Header 2lt19 On Each Side Of Garage Door Also Two Straps Missing On Header |
Matt Forsyth |
1/3/2022 |
Passed: Building - Framing |
|
Matt Forsyth |
1/26/2022 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/26/2022 |
Failed: Mechanical - Rough In |
Need Nail Plate On Dryer Vent Double Plate At Top Of Wall We'll Check Off On Insulation Inspection |
Matt Forsyth |
1/26/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/26/2022 |
Passed: Building - Insulation |
|
Troy Crews |
2/4/2022 |
Passed: Mechanical - Rough In |
Item Corrected |
Troy Crews |
2/4/2022 |
Septic Release Inspection |
|
Health Dept |
3/11/2022 |
Failed: Electrical - Permanent Power |
No Access To Property |
Matt Forsyth |
5/27/2022 |
Failed: Electrical - Permanent Power |
No Dead Cover On Panel In House Also Work On Service Disconnect Out Side Not Complete |
Matt Forsyth |
6/2/2022 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
6/6/2022 |
Release to power company |
|
Troy Crews |
6/6/2022 |
Release to power company |
Changed Power Company From Clay To Fpl |
Melissa Garber |
6/7/2022 |
Failed: Building - Final |
Electrical Panel Not Labeled |
Matt Forsyth |
7/6/2022 |
Failed: Building - Final |
Electricians Need To Go Over The House And Do A Live Check Before Scheduling A Inspection. |
Matt Forsyth |
7/7/2022 |
Failed: Building - Final |
Same Problem As Yesterday. Electrician Said He Fixed |
Matt Forsyth |
7/8/2022 |
Passed: Building - Final |
|
Matt Forsyth |
7/12/2022 |