| Passed: Building - Footer |
|
Matt Forsyth |
11/18/2021 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
11/18/2021 |
| Rescheduled 1/3/2022:Building - Slab |
|
Melissa Garber |
12/22/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
12/23/2021 |
| Passed: Building - Slab |
|
Matt Forsyth |
1/3/2022 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
1/27/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
2/4/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
2/4/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
2/4/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
2/24/2022 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
2/24/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Need Water Test On Bathtub. Can Do Water Test At Insulation Inspection |
Matt Forsyth |
2/24/2022 |
| Passed: Building - Insulation |
|
Matt Forsyth |
3/7/2022 |
| Failed: Electrical - Permanent Power |
Electrical Panel Not Labeled Or Made Up (breakers) Need Septic Release |
Matt Forsyth |
5/11/2022 |
| Passed: Electrical - Permanent Power |
Septic Needed |
Matt Forsyth |
5/12/2022 |
| Release to power company |
|
Melissa Garber |
5/26/2022 |
| Septic Release Inspection |
|
Health Dept |
5/26/2022 |
| Passed: Building - Final |
Need Proof Of Mechanical Ventilation On Hvac Ok To Start Moving In |
Matt Forsyth |
7/6/2022 |
| Passed: Building - Final |
Item Addressed |
Matt Forsyth |
7/6/2022 |