Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Special Foundation |
Troy Crews |
9/14/2021 |
Passed: Engineering - Setbacks |
Confirm With Surveyor |
Troy Crews |
9/14/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Done 9-23-21 |
Troy Crews |
9/23/2021 |
Passed: Building - Slab |
|
Troy Crews |
10/13/2021 |
Passed: Building - Roof Decking |
|
Troy Crews |
10/28/2021 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
10/28/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
Reminder Porch Post Need Strapping |
Troy Crews |
12/13/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
40 Lbs Pressure |
Troy Crews |
12/22/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
1/10/2022 |
Passed: Building - Strapping |
|
Troy Crews |
1/10/2022 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/10/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
1/10/2022 |
Failed: Building - Framing |
Check All Porch Post Buckets For Nail Off. Also No Header On Upstairs Window Need Engineering |
Troy Crews |
1/11/2022 |
Failed: Mechanical - Rough In |
Bath Fan Duct For Upstairs Bath That Goes To Back Porch Soffit Damaged Needs To Be Replaced |
Troy Crews |
1/11/2022 |
Passed: Building - Framing |
Items Corrected, Letter For Dormer Window. |
Troy Crews |
1/24/2022 |
Passed: Mechanical - Rough In |
Duct Extended. |
Troy Crews |
1/24/2022 |
Passed: Building - Insulation |
|
Troy Crews |
3/1/2022 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
6/22/2022 |
Release to power company |
|
Troy Crews |
6/22/2022 |
Passed: Building - Final |
Bonus Room Upstairs Not Approved For Sleeping Room, Need Blower Door Test For Release Of Co |
Troy Crews |
10/26/2022 |