| Passed: Engineering - Setbacks |
|
Anthony Aslan |
9/2/2021 |
| Passed: Building - Footer |
Need Porta Potty |
Anthony Aslan |
9/2/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
10/7/2021 |
| Passed: Building - Slab |
Per Conversation Need Initial Termite Treatment |
Anthony Aslan |
10/26/2021 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
11/8/2021 |
| Release to power company |
|
Anthony Aslan |
11/8/2021 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
1/5/2022 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
1/5/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
2/7/2022 |
| Failed: Building - Framing |
Anchors Missing At Splices. Reschedule When Electrical. |
Anthony Aslan |
2/7/2022 |
| Failed: Mechanical - Rough In |
Exhaust Fans Piping Not Allowed In Attic. Needs To Be Metal |
Anthony Aslan |
2/7/2022 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
2/24/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
2/24/2022 |
| Passed: Building - Framing |
|
Anthony Aslan |
2/24/2022 |
| Passed: Building - Insulation |
|
Anthony Aslan |
3/2/2022 |
| Septic Release Inspection |
|
Health Dept |
5/16/2022 |