Inspection |
Notes |
Performed By |
Date |
Failed: Building - Footer |
Need Proof Of Front Setback Compliance |
Troy Crews |
8/26/2021 |
Failed: Engineering - Setbacks |
Front Setback |
Troy Crews |
8/26/2021 |
Passed: Building - Footer |
Moved Back To Meet Setback, Have Surveyor Confirm Prior To Block Work |
Troy Crews |
8/31/2021 |
Passed: Engineering - Setbacks |
|
Troy Crews |
8/31/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
9/24/2021 |
Passed: Building - Slab |
|
Troy Crews |
9/24/2021 |
Failed: Building - Framing |
Need Additional Strapping All Truss Uplift Over 585 Pounds, Need Stud Pack Under All Bearing Points T-10 Truss, Need More Nails In Truss Buckets Garage Area. |
Troy Crews |
11/2/2021 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
11/2/2021 |
Failed: Mechanical - Rough In |
No Duct On Range Hood Vent Thru Roof |
Troy Crews |
11/2/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
11/2/2021 |
Passed: Building - Framing |
|
Troy Crews |
11/16/2021 |
Passed: Mechanical - Rough In |
|
Troy Crews |
11/16/2021 |
Passed: Building - Insulation |
|
Troy Crews |
11/29/2021 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
2/17/2022 |
Release to power company |
|
Troy Crews |
2/17/2022 |
Failed: Building - Final |
Need House Numbers, Need Blowerdoor Test, Need Access To Attic To Check Insulation, Or Insulation Certificate, Need To Correct Electrical In Bathrooms One Receptacle Is In The Wall. |
Troy Crews |
4/27/2022 |
Failed: Building - Final |
Need To Correct Electrical In Bathrooms Cant Use Receptacle As Junction Box In Wall Must Be Accessible, Also Need Elevation Confirmation From Surveyor. |
Troy Crews |
5/3/2022 |
Passed: Building - Final |
Boxes In Wall For Flush Mount Mirror, Holes To Be Left For Access Per Builder. Need Elevation Letter Entered For Release Of C.o. |
Troy Crews |
5/4/2022 |
Certificate-Release Certificate |
Elevation Recieved |
Troy Crews |
10/24/2023 |