Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
8/16/2021 |
Passed: Building - Footer |
|
Anthony Aslan |
8/16/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
10/7/2021 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
10/13/2021 |
Release to power company |
|
Anthony Aslan |
10/13/2021 |
Passed: Building - Slab |
|
Anthony Aslan |
10/14/2021 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
10/28/2021 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
10/28/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
Post & Gable |
Anthony Aslan |
10/28/2021 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
1/24/2022 |
Failed: Mechanical - Rough In |
Screws Missing On Kitchen Exhaust Pipe Joint, Gasket Hanging Down Boot In Living Room. |
Anthony Aslan |
1/24/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
1/24/2022 |
Failed: Plumbing/Gas - Tub Set/Shower Pan |
No Pressure On Gas Piping |
Anthony Aslan |
1/24/2022 |
Failed: Building - Framing |
Electrical Service More Than 50% Bearing Top Plate Drilled, Check Anchors Missing Some Bottom Plate Splices |
Anthony Aslan |
1/24/2022 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
1/27/2022 |
Passed: Mechanical - Rough In |
Correction Made |
Anthony Aslan |
1/27/2022 |
Passed: Building - Framing |
Correction Made |
Anthony Aslan |
1/27/2022 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Pressure On Gas |
Anthony Aslan |
1/27/2022 |
Passed: Building - Insulation |
Walls, Vaults, Knee Walls Only |
Anthony Aslan |
2/1/2022 |
Cancelled: Building - Vertical Cells/Columns |
|
Anthony Aslan |
3/4/2022 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
3/4/2022 |
Failed: Building - Footer |
Need Pictures Of Post Holes And If No Pictures Need Letter From Engineer |
Anthony Aslan |
3/4/2022 |
Passed: Building - Footer |
Rec'd Pictures |
Anthony Aslan |
4/5/2022 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
4/5/2022 |
Passed: Building - Slab |
|
Anthony Aslan |
4/5/2022 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
5/12/2022 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
9/22/2022 |
Release to power company |
|
Melissa Garber |
10/13/2022 |
Septic Release Inspection |
|
Health Dept |
10/13/2022 |
Passed: Building - Final |
Lights In Bed Rooms Not Coming On |
Anthony Aslan |
12/6/2022 |
Certificate-Release Certificate |
|
Anthony Aslan |
12/14/2022 |