Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Solar Power System Permit
Address 189 SW PHEASANT WAY
LAKE CITY, FL 32024
Parcel #: 03023-119
Acres: 0.50
Owner: De La Rosa Randolfi & Pinares Maricel
Subdivision: Callaway Phase 1
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 49681
Permit #: 000042242
Related Permit:
Submitted: Friday, June 18, 2021
Issued: Wednesday, June 30, 2021
Expires: Tuesday, July 20, 2021
Completed: Tuesday, July 20, 2021
Status: Completed
Septic Release? na
Notes:

Job Details
PV Type Utility Interactive PV System- (DC to AC with utility connection)
Grounding N.E.C. Chapter 690
AC Options Exposed
AC Options (Cont..) In Conduit;THWN-2
Where are the panels mounted? Roof Mounted
Power Company Clay Electric
Residential or Commercial? Residential
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Fema map number 12023C0289D
Review Notes
6/18/2021 Application pending.
6/22/2021 Point Review - Printed-Online Application NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE NEEDS TO BE SIGNED OR E-SIGNED, NOT A FONT *ELECTRICIAN SUB VF *MENDOZA UPDATED WORKERS COMP PRIOR TO INSPECTIONS: RECORDED NOC
6/22/2021 Point Review - Reviewed NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE NEEDS TO BE SIGNED OR E-SIGNED, NOT A FONT *ELECTRICIAN SUB VF *MENDOZA UPDATED WORKERS COMP PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Plan Review - Electrical Approved PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Plan Review - Building Approved PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Plan Review - Reviewed PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Zoning Review - Reviewed PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Final Review - Reviewed PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Final Review - Payment Needed PRIOR TO INSPECTIONS: RECORDED NOC
6/30/2021 Permit Issued Permit #000042242 created and approved.
Contractors
Name/ Business License Title Role
Rafael Mendoza
Go Solar Power Llc
CVC56962 Cert. Solar Contractor
Dean A Hodge
Go Solar Power Llc
EC13007879 Cert. Electrical Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Solar - Solar Final Matt Forsyth 7/20/2021
Release to power company Matt Forsyth 7/20/2021