Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
5/28/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
5/28/2021 |
Rescheduled 6/9/2021:Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
6/8/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
6/9/2021 |
Passed: Building - Slab |
|
Matt Forsyth |
6/16/2021 |
Failed: Electrical - Temporary Service |
Need Loose Wires In Breaker Box Removed |
Matt Forsyth |
6/16/2021 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
8/4/2021 |
Passed: Building - Framing |
|
Matt Forsyth |
9/3/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
9/3/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
9/3/2021 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
9/3/2021 |
Passed: Building - Insulation |
Walls Only |
Anthony Aslan |
9/8/2021 |
Failed: Mechanical - Rough In |
Missing Hanging Straps On Ducts, Missing Strapping On Exhaust Fan Ducts. |
Anthony Aslan |
9/8/2021 |
Passed: Mechanical - Rough In |
Items Addressed |
Matt Forsyth |
9/9/2021 |
Septic Release Inspection |
|
Health Dept |
10/14/2021 |
Passed: Engineering - Initial Driveway |
|
Jones, Richard |
10/25/2021 |
Passed: Engineering - Final Driveway |
|
Jones, Richard |
10/25/2021 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
10/25/2021 |
Release to power company |
|
Matt Forsyth |
10/25/2021 |
Cancelled: Re-Roof - Final |
|
Melissa Garber |
11/8/2021 |
Failed: Building - Final |
1) Toilets Not Set
2) Bath Room Sinks Not Plumed In
3) Master Shower Not Complete
4) Need Disconnect Or Locking Device For Breaker Of Ahu And Water Heater
5) Hose Bib Back Flow Not Installed
6) Locking Caps Condenser
7)trimin Garage Floor Could Not Verify Attic Insulation |
Anthony Aslan |
11/9/2021 |
Passed: Building - Insulation |
Ceiling |
Matt Forsyth |
11/12/2021 |
Passed: Building - Final |
|
Matt Forsyth |
11/12/2021 |