| Septic Release Inspection |
|
Health Dept |
4/26/2021 |
| Passed: Building - Footer |
|
Troy Crews |
6/1/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
6/1/2021 |
| Failed: Plumbing/Gas - 1st Underground Rough–In |
All Underslab Waterlines Need To Be Under Pressure |
Matt Forsyth |
6/30/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
7/1/2021 |
| Passed: Building - Slab |
|
Matt Forsyth |
7/15/2021 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
9/8/2021 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/8/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
9/8/2021 |
| Failed: Building - Framing |
Missing Several Truss Straps Will Check On Next Inspection |
Matt Forsyth |
9/8/2021 |
| Failed: Building - Ext Strapping/Wall Sheathing |
Gable End Strapping Missing |
Matt Forsyth |
10/27/2021 |
| Failed: Building - Framing |
Front. Porch Beam Nailed Both Sides |
Matt Forsyth |
10/27/2021 |
| Passed: Building - Strapping |
Interior Strapping |
Matt Forsyth |
10/27/2021 |
| Cancelled: Building - Wall Sheathing |
|
Matt Forsyth |
10/27/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
10/27/2021 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
10/27/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
10/27/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
11/8/2021 |
| Passed: Building - Framing |
|
Troy Crews |
11/8/2021 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
4/11/2022 |
| Release to power company |
|
Matt Forsyth |
4/11/2022 |