| Passed: Building - Footer |
|
Troy Crews |
5/21/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
5/21/2021 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
5/21/2021 |
| Release to power company |
|
Troy Crews |
5/21/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
6/3/2021 |
| Passed: Building - Slab |
|
Troy Crews |
6/9/2021 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
6/21/2021 |
| Release to power company |
|
Matt Forsyth |
6/21/2021 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
7/27/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
7/27/2021 |
| Passed: Building - Framing |
|
Matt Forsyth |
7/27/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
8/6/2021 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
8/6/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
8/6/2021 |
| Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
8/10/2021 |
| Passed: Electrical - Permanent Power |
Need Septic And Driveway Release |
Matt Forsyth |
9/24/2021 |
| Septic Release Inspection |
Need Driveway Release |
Health Dept |
9/24/2021 |
| Release to power company |
|
Melissa Garber |
9/30/2021 |
| Failed: Building - Final |
Plumbing Work Needs To Be Completed Also Need A Blower Door Test |
Matt Forsyth |
10/11/2021 |
| Passed: Building - Final |
|
Matt Forsyth |
10/12/2021 |