| Cancelled: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
7/16/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
7/16/2021 |
| Failed: Building - Slab |
Footer Detail Calls For 18" W X 22"d Min., Footer Is 12" X 16" |
Anthony Aslan |
7/22/2021 |
| Passed: Building - Monolithic Slab |
Architect Approved Metal Building Plan For Footer Size |
Troy Crews |
7/29/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
7/29/2021 |
| Passed: Electrical - Temporary Service |
Will Call In Again For Permanent When Building Complete |
Troy Crews |
3/22/2022 |
| Release to power company |
|
Troy Crews |
3/22/2022 |
| Passed: Building - Framing |
|
Anthony Aslan |
3/24/2022 |
| Cancelled: Electrical - Permanent Power |
|
Anthony Aslan |
8/19/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
8/19/2022 |
| Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
11/15/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
12/13/2022 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
12/13/2022 |
| Passed: Building - Insulation |
|
Anthony Aslan |
12/13/2022 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
12/13/2022 |
| Passed: Building - Final |
Need Septic Release, Afci Breaker |
Anthony Aslan |
3/9/2023 |
| Septic Release Inspection |
|
Health Dept |
6/9/2023 |
| Certificate-Release Certificate |
|
Anthony Aslan |
6/12/2023 |