Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
6/3/2021 |
Release to power company |
|
Anthony Aslan |
6/3/2021 |
Passed: Building - Footer |
|
Anthony Aslan |
6/22/2021 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
6/22/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
7/13/2021 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
7/13/2021 |
Passed: Building - Slab |
|
Anthony Aslan |
8/4/2021 |
Passed: Building - Masonry Wall Reinforcing |
|
Troy Crews |
9/9/2021 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
10/26/2021 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
10/26/2021 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
1/20/2022 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
3/10/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
3/10/2022 |
Failed: Mechanical - Rough In |
Mastic Supply And Returns, Missing Foam On Some Supplies And Returns |
Anthony Aslan |
3/10/2022 |
Septic Release Inspection |
|
Health Dept |
3/15/2022 |
Passed: Building - Framing |
Rec'd Engineer Letter 3-1-2022 |
Anthony Aslan |
3/21/2022 |
Passed: Building - Insulation |
|
Anthony Aslan |
3/21/2022 |
Passed: Mechanical - Rough In |
|
Anthony Aslan |
3/21/2022 |
Passed: Electrical - Permanent Power |
|
Anthony Aslan |
5/23/2022 |
Release to power company |
|
Anthony Aslan |
5/23/2022 |
Passed: Building - Final |
Hose Bibs, Stair Hand Rail |
Anthony Aslan |
8/24/2022 |
Certificate-Release Certificate |
Recv'd Hand Rail Pictures |
Anthony Aslan |
8/25/2022 |
Cancelled: Building - Final |
|
Anthony Aslan |
8/25/2022 |