Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/10/2021 |
Passed: Building - Footer |
|
Anthony Aslan |
5/10/2021 |
Rescheduled 5/17/2021:Building - Slab |
|
Anthony Aslan |
5/17/2021 |
Passed: Building - Slab |
Leave Concrete Tickets Showing Fiber Mesh If Wire Mesh Is Not Used |
Anthony Aslan |
5/17/2021 |
Passed: Building - Lintel/Tie Beam |
|
Anthony Aslan |
6/3/2021 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
7/14/2021 |
Passed: Building - Roof Decking |
Need Repair For A03 Truss |
Anthony Aslan |
7/14/2021 |
Passed: Building - Framing |
Truss Corrected |
Anthony Aslan |
9/16/2021 |
Failed: Mechanical - Rough In |
Kitchen Exhaust Missing Screws In Joints, Make-up Air Needs Automatic Damper. |
Anthony Aslan |
9/16/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
9/16/2021 |
Failed: Electrical - 1st Underground Rough–In |
Wire Needs To Be In Conduit Or Changed Out To Uf Under Ground Wire, Under Porches. |
Anthony Aslan |
9/16/2021 |
Failed: Building - Insulation |
Gate Locked |
Anthony Aslan |
10/13/2021 |
Failed: Electrical - 1st Underground Rough–In |
Gate Locked |
Anthony Aslan |
10/13/2021 |
Failed: Mechanical - Rough In |
Gate Locked |
Anthony Aslan |
10/13/2021 |
Passed: Building - Insulation |
|
Anthony Aslan |
10/15/2021 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
10/15/2021 |
Passed: Mechanical - Rough In |
|
Anthony Aslan |
10/15/2021 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
2/17/2022 |
Release to power company |
|
Melissa Garber |
3/8/2022 |
Septic Release Inspection |
|
Health Dept |
3/8/2022 |
Passed: Building - Final |
Gfci Outlet In Laundry, Kitchen Back Splash Outlets Not Gfci Protected |
Anthony Aslan |
5/10/2022 |
Certificate-Release Certificate |
Contingent On Gfic In Noted Areas |
Anthony Aslan |
5/13/2022 |