Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
4/8/2021 |
Passed: Building - Footer |
|
Anthony Aslan |
4/8/2021 |
Passed: Engineering - Setbacks |
25' And 10' Confirmed By Surveyor Very Tight Lots. |
Anthony Aslan |
4/8/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
5/10/2021 |
Passed: Building - Slab |
|
Troy Crews |
5/17/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
6/24/2021 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
6/24/2021 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
6/24/2021 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
6/24/2021 |
Cancelled: Building - Framing |
|
Anthony Aslan |
6/24/2021 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
7/7/2021 |
Failed: Mechanical - Rough In |
Dryer Vent Can Not Be Deformed Through Top Plate. |
Anthony Aslan |
7/7/2021 |
Failed: Building - Insulation |
Need Picture Of Strap For Top Plate Where Dryer Pass Through. |
Anthony Aslan |
7/23/2021 |
Building-Framing |
|
Anthony Aslan |
7/30/2021 |
Passed: Building - Insulation |
|
Anthony Aslan |
7/30/2021 |
Passed: Mechanical - Rough In |
Strap On Dryer At Top Plate |
Anthony Aslan |
7/30/2021 |
Cancelled: Electrical - Permanent Power |
|
Anthony Aslan |
8/24/2021 |
Passed: Electrical - Permanent Power |
Need Septic And Culvert Finals |
Troy Crews |
9/1/2021 |
Septic Release Inspection |
|
Health Dept |
9/17/2021 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Melissa Garber |
9/23/2021 |
Release to power company |
|
Melissa Garber |
10/5/2021 |
Passed: Engineering - Final Driveway |
|
Jones, Richard |
10/5/2021 |
Passed: Building - Final |
Need Hose Bid Back Flow, Missing Outlet Covers In Kitchen, |
Anthony Aslan |
12/3/2021 |
Certificate-Release Certificate |
Rec'd Pictures |
Anthony Aslan |
12/8/2021 |