New Residential Construction

205 SW GOVERNORS GLN
LAKE CITY, FL 32024

Permit #
000041584
Application #
48486
Status Completed
  1. Submitted Feb 23, 2021
  2. Issued Mar 23, 2021
  3. Expires Jul 5, 2022
  4. Completed Jan 6, 2022

Property

Parcel #
03406-206
Owner
Nickelson Dale
Acres
2.50
Subdivision
Rose Creek Plantation
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0383D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
2
Heated Area (Sqft)
3477
Total Area (Sqft)
5255
Building Height
26
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0231

Status & Review History

  1. Point Review - Printed-Online Application
  2. Final Review - Documents Required
  3. Zoning Review - Reviewed
  4. Plan Review - Reviewed
  5. Final Review - Documents Required
  6. Permit Issued
  7. Final Review - Payment Needed
  8. Final Review - Payment Needed

Contractors

  • Aaron Nickelson

    Aaron Marc Homes

    License
    CBC1258040
    Title
    Building Contractor
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Benjamin L Sparks

    Line Electric Company Llc

    License
    EC13009101
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Stephen M Brisbois

    Epic Ac Service

    License
    CAC1819412
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

Inspections

  1. Mar 26, 2021

    Failed: Building - Footer

    Some Of Rebar Chairs Are To Far Apart Or Crushed Down.no Portable Toilet On Jobsite

    Inspected by Matt Forsyth

  2. Mar 26, 2021

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Mar 29, 2021

    Passed: Building - Footer

    Inspected by Matt Forsyth

  4. Mar 29, 2021

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  5. Apr 8, 2021

    Failed: Electrical - Temporary Service

    Temp Pole Requires Ground Rod

    Inspected by Matt Forsyth

  6. May 17, 2021

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  7. May 24, 2021

    Passed: Building - Slab

    Inspected by Matt Forsyth

  8. May 25, 2021

    Cancelled: Building - Slab

    Inspected by Matt Forsyth

  9. Jun 1, 2021

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  10. Jun 1, 2021

    Release to power company

    Inspected by Troy Crews

  11. Jul 13, 2021

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  12. Jul 13, 2021

    Failed: Building - Wall Sheathing

    Shiners Need To Be Removed And Sheating Re-nailed

    Inspected by Matt Forsyth

  13. Jul 27, 2021

    Failed: Building - Framing

    Lateral Bracing Needed On Balcony Floor Scissor Trusses. Fireblocking Needed In Kitchen Soffit Drop. H25 Or Equivalent On Trusses Bo5bo6

    Inspected by Matt Forsyth

  14. Aug 18, 2021

    Failed: Building - Framing

    Need Fire Blocking Where Ceiling Was Lowered Above Shower

    Inspected by Matt Forsyth

  15. Aug 18, 2021

    Failed: Electrical - 2nd Rough-In

    Need Nail Plates In Garage For Service Entrance Conductors In Two Places

    Inspected by Matt Forsyth

  16. Aug 18, 2021

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  17. Aug 18, 2021

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  18. Sep 10, 2021

    Passed: Building - Framing

    Inspected by Matt Forsyth

  19. Sep 10, 2021

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  20. Dec 17, 2021

    Failed: Electrical - Permanent Power

    Need Breaker Panel Cleaned Up And Septic Release To Release Power

    Inspected by Matt Forsyth

  21. Dec 21, 2021

    Release to power company

    Inspected by Melissa Garber

  22. Dec 21, 2021

    Passed: Electrical - Permanent Power

    Need Septic Release From Environmental

    Inspected by Matt Forsyth

  23. Dec 21, 2021

    Septic Release Inspection

    Inspected by Health Dept

  24. Dec 30, 2021

    Rescheduled 1/3/2022:Building - Final

    Inspected by Matt Forsyth

  25. Jan 3, 2022

    Failed: Building - Final

    Need Blower Door Test And An Access Door For Air Handler In Attic(both)

    Inspected by Matt Forsyth

  26. Jan 6, 2022

    Passed: Building - Final

    Inspected by Matt Forsyth