Inspection |
Notes |
Performed By |
Date |
Septic Release Inspection |
|
Health Dept |
4/14/2021 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Need 3/4 Of An Inch Clear Off Form Boards |
Matt Forsyth |
5/4/2021 |
Failed: Building - Slab |
Pipe Coming Thru Slab Needs Clearance From Formwork.this Was Not Taken Care Of From Last Inspection. |
Matt Forsyth |
5/13/2021 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
5/13/2021 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
5/13/2021 |
Passed: Building - Slab |
|
Matt Forsyth |
5/13/2021 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Item Addressed |
Matt Forsyth |
5/13/2021 |
Passed: Building - Framing |
|
Matt Forsyth |
6/30/2021 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
6/30/2021 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
6/30/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
6/30/2021 |
Failed: Building - Insulation |
Will Need To Re Inspect After Windows And Doors Are Installed |
Matt Forsyth |
7/6/2021 |
Passed: Building - Insulation |
Electrical Panel Needs To Be Moved From Bathroom |
Anthony Aslan |
7/16/2021 |
Passed: Building - Framing |
|
Anthony Aslan |
7/16/2021 |
Passed: Electrical - 2nd Rough-In |
Electrical Service Panel Moved |
Matt Forsyth |
7/26/2021 |
Failed: Electrical - Permanent Power |
Power Must Come From Main House, Also Need To Do Swale On East Side Prior To Final. |
Troy Crews |
9/16/2021 |
Failed: Building - Final |
Need Blower Door Test, Landing Pads For Exterior Doors, Repair Soil Around Condenser Unit And Secure Soil On East Side Washing Toward Adjacent Property. |
Troy Crews |
10/6/2021 |
Passed: Building - Final |
Pictures Sent Of Landings And Silt Fence, Also Blower Door Test Received. |
Troy Crews |
10/28/2021 |