Permit Details

Permit Search

Permit

Remodel

1134 SW CUSTOM MADE CIR
LAKE CITY, FL 32024

Permit #
000041562
Application #
48556
Status Completed
  1. Submitted Mar 4, 2021
  2. Issued Mar 22, 2021
  3. Expires Jan 5, 2022
  4. Completed Jul 9, 2021

Property

Parcel #
09280-156
Owner
Radwan Mohamed A
Acres
4.48
Subdivision
Oaks Of Lake City Phase 1
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0395C
Type of Structure
House
Commercial or Residential?
Residential
Description of the work being performed:
INTERIOR REMODEL
Septic#
21-0189
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code

Status & Review History

  1. Application pending.
  2. Point Review - Printed-Online Application
  3. Point Review - Printed-Online Application
  4. Plan Review - Reviewed
  5. Zoning Review - Reviewed
  6. Final Review - Reviewed
  7. Final Review - Payment Needed
  8. Permit Issued

Contractors

  • Bryan Zecher

    Bryan Zecher Construction Inc

    License
    CBC054575
    Title
    Cert.building Contractor
    Role
    Contractor
  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Anthony R Franks

    Franks & Lane Heating And Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles Ii

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Mar 3, 2021

    Septic Release Inspection

    Inspected by Health Dept

  2. Apr 7, 2021

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  3. Apr 7, 2021

    Passed: Building - Slab

    Inspected by Troy Crews

  4. Apr 7, 2021

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  5. Apr 21, 2021

    Passed: Building - Framing

    Inspected by Troy Crews

  6. Apr 21, 2021

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  7. Apr 21, 2021

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  8. Apr 22, 2021

    Passed: Building - Insulation

    Inspected by Troy Crews

  9. Jul 9, 2021

    Passed: Building - Final

    Inspected by Troy Crews