| Cancelled: Building - Footer |
|
Melissa Garber |
3/17/2021 |
| Cancelled: Engineering - Setbacks |
|
Melissa Garber |
3/17/2021 |
| Rescheduled 3/18/2021:Electrical - Temporary Service |
|
Troy Crews |
3/17/2021 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
3/18/2021 |
| Release to power company |
|
Troy Crews |
3/18/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
5/3/2021 |
| Passed: Building - Slab |
|
Troy Crews |
5/12/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
7/13/2021 |
| Passed: Building - Framing |
|
Troy Crews |
7/13/2021 |
| Passed: Building - Roof Decking |
|
Troy Crews |
7/13/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
7/27/2021 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
7/27/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
7/27/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
8/12/2021 |
| Passed: Electrical - Permanent Power |
Need Septic Final |
Troy Crews |
11/10/2021 |
| Release to power company |
|
Laurie Hodson |
11/19/2021 |
| Septic Release Inspection |
|
Health Dept |
11/19/2021 |
| Passed: Building - Final |
|
Troy Crews |
3/4/2022 |