Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
2/26/2021 |
Passed: Building - Monolithic Slab |
|
Anthony Aslan |
3/4/2021 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
3/4/2021 |
Passed: Building - Lintel/Tie Beam |
|
Anthony Aslan |
3/26/2021 |
Passed: Building - Masonry Wall Reinforcing |
|
Anthony Aslan |
3/26/2021 |
Failed: Electrical - Temporary Service |
No Temp Pole |
Anthony Aslan |
3/26/2021 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
3/31/2021 |
Release to power company |
|
Anthony Aslan |
3/31/2021 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
4/6/2021 |
Passed: Building - Strapping |
|
Anthony Aslan |
4/6/2021 |
Passed: Building - Framing |
|
Anthony Aslan |
4/6/2021 |
Cancelled: Electrical - 2nd Rough-In |
No Ready |
Anthony Aslan |
4/15/2021 |
Cancelled: Mechanical - Rough In |
No Ready |
Anthony Aslan |
4/15/2021 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
No Ready |
Anthony Aslan |
4/15/2021 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/20/2021 |
Passed: Building - Insulation |
Partial Inspection, Check At Final |
Anthony Aslan |
4/20/2021 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
4/20/2021 |
Failed: Mechanical - Rough In |
Dryer Box Pipe Not Through Box |
Anthony Aslan |
4/20/2021 |
Cancelled: Building - Insulation |
|
Anthony Aslan |
5/7/2021 |
Passed: Building - Framing |
Windows Installed |
Anthony Aslan |
5/7/2021 |
Passed: Mechanical - Rough In |
Dryer Box Lifted |
Anthony Aslan |
5/7/2021 |
Passed: Electrical - Permanent Power |
Need Septic Releasr |
Anthony Aslan |
7/22/2021 |
Release to power company |
|
Laurie Hodson |
7/26/2021 |
Septic Release Inspection |
|
Health Dept |
7/26/2021 |
Passed: Building - Final |
Insulation Checked Good |
Anthony Aslan |
8/18/2021 |
(Requested) Building-Fire Rated Wall |
|
|
|
(Requested) Electrical -2nd Rough-In |
|
|
|
(Requested) Plumbing/Gas-2nd Rough-In |
|
|
|
(Requested) Electrical -2nd Rough-In |
|
|
|
(Requested) Plumbing/Gas-2nd Rough-In |
|
|
|
(Requested) Electrical -Permanent Power |
|
|
|
(Requested) Electrical -2nd Rough-In |
|
|
|
(Requested) Plumbing/Gas-2nd Rough-In |
|
|
|
(Requested) Electrical -Permanent Power |
|
|
|
(Requested) Electrical -2nd Rough-In |
|
|
|
(Requested) Plumbing/Gas-2nd Rough-In |
|
|
|