Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Mccormick, David |
8/5/2020 |
Passed: Building - Footer |
|
Matt Forsyth |
8/5/2020 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/5/2020 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
8/18/2020 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
8/20/2020 |
Release to power company |
|
Matt Forsyth |
8/20/2020 |
Passed: Building - Slab |
Need Permit Posted |
Matt Forsyth |
8/20/2020 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/9/2020 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
9/28/2020 |
Passed: Building - Framing |
|
Matt Forsyth |
10/13/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
11/2/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
11/2/2020 |
Failed: Mechanical - Rough In |
Exhaust Fan Not Connected To Ductwork |
Matt Forsyth |
11/2/2020 |
Cancelled: Electrical - 2nd Rough-In |
|
Matt Forsyth |
11/3/2020 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
11/3/2020 |
Cancelled: Electrical - 2nd Rough-In |
|
Matt Forsyth |
11/3/2020 |
Failed: Mechanical - Rough In |
Item's Not Corrected |
Matt Forsyth |
11/3/2020 |
Cancelled: Mechanical - Rough In |
|
Matt Forsyth |
11/3/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
11/4/2020 |
Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
11/6/2020 |
Septic Release Inspection |
|
Health Dept |
6/16/2021 |
Passed: Electrical - Permanent Power |
Need Driveway Final, Also Need Elevation Confirmation Prior To C.o. |
Troy Crews |
8/20/2021 |
Release to power company |
Need Elevation Confirmation Prior To C/o |
Melissa Garber |
8/31/2021 |
Passed: Engineering - Final Driveway |
|
Mccormick, David |
8/31/2021 |
Failed: Building - Final |
Need Elevation Confirmation Certificate Need Blower Door Test Proof Of Termite Treatment |
Matt Forsyth |
11/4/2021 |
Passed: Building - Final |
|
Matt Forsyth |
11/12/2021 |