Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
5/21/2019 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
5/21/2019 |
Passed: Electrical - Footer Steel & Grounding |
|
Matt Forsyth |
5/21/2019 |
Passed: Building - Vertical Cells/Columns |
|
Tommy Matthews |
5/30/2019 |
Passed: Building - Lintel/Tie Beam |
|
Tommy Matthews |
5/30/2019 |
Cancelled: Building - Framing |
James Cancelled Due To Rain |
Laurie Hodson |
6/7/2019 |
Passed: Building - Framing |
Floor Framing |
Troy Crews |
6/10/2019 |
Failed: Building - Roof Decking |
Spacing Not Correct, Roof Deck Not Complete, |
Tommy Matthews |
7/2/2019 |
Passed: Building - Roof Decking |
|
Troy Crews |
7/5/2019 |
Passed: Building - Ext Strapping/Wall Sheathing |
Nail In Between Deep Nails |
Troy Crews |
7/9/2019 |
Passed: Plumbing/Gas - Rough In |
|
Tommy Matthews |
7/23/2019 |
Cancelled: Building - Framing |
|
Matt Forsyth |
7/30/2019 |
Passed: Building - Framing |
|
Matt Forsyth |
7/31/2019 |
Failed: Mechanical - Rough In |
Not Complete. |
Tommy Matthews |
2/26/2020 |
Failed: Electrical - 2nd Rough-In |
Where Is Service Entrance Raceway Or Entrance Cable? |
Tommy Matthews |
2/26/2020 |
Passed: Building - Insulation |
|
Matt Forsyth |
4/6/2020 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/6/2020 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
4/6/2020 |
Passed: Plumbing/Gas - 2nd Rough-In |
Water Test Has Been Performed On All 3 Bathtubs |
Matt Forsyth |
4/6/2020 |
Septic Release Inspection |
|
Health Dept |
10/7/2021 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
10/7/2021 |
Release to power company |
|
Matt Forsyth |
10/7/2021 |
Passed: Building - Final |
Need Final Termite Treatment To Complete And Release Co |
Matt Forsyth |
10/7/2021 |
Certificate-Release Certificate |
|
Matt Forsyth |
11/24/2021 |