| Passed: Building - Footer |
|
Troy Crews |
1/5/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/5/2021 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
1/11/2021 |
| Release to power company |
|
Troy Crews |
1/11/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
2/8/2021 |
| Passed: Building - Slab |
|
Troy Crews |
2/25/2021 |
| Passed: Building - Roof Decking |
Need To Call Exterior Strapping In |
Anthony Aslan |
4/13/2021 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
4/13/2021 |
| Passed: Building - Wall Sheathing |
Need To Call Exterior Strapping In |
Anthony Aslan |
4/13/2021 |
| Passed: Building - Framing |
|
Troy Crews |
4/20/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
5/3/2021 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
5/3/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
5/3/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
5/7/2021 |
| Passed: Electrical - Permanent Power |
Need Septic |
Troy Crews |
7/14/2021 |
| Septic Release Inspection |
|
Health Dept |
7/20/2021 |
| Release to power company |
Septic And Driveway Completed |
Laurie Hodson |
7/26/2021 |
| Passed: Building - Final |
Release Pending Picture Of Step In Garage. |
Troy Crews |
9/20/2021 |