Permit Information

Additions Permit

Address 389 NW QUINTEN ST
LAKE CITY, FL 32055
Parcel #: 05068-000
Acres:38.47
Owner:Columbia County, Florida
Subdivision:
Zoning:I
Flood Zone:X
District:1
Application #:47124
Permit #: 000040782
Related Permit:
Submitted:Thursday, October 8, 2020
Issued:Friday, October 23, 2020
Expires:Tuesday, March 15, 2022
Completed:Tuesday, March 15, 2022
Status: Completed
Septic Release? Yes

Notes

APPROVED SPECIAL EXCEPTION (SE0622) FOR DETENTION FACILITY EXPANSION

Job Details

Elevation regulation Site & Development Plan
Finished floor requirement 179.1'
Requirement needed By Nailing Inspection
Document needed is a Surveyor letter giving the Finished Floor Elevation
Document receieved Yes
Fema map number 12023C0285D
Description of addition: Dormitory Pod for existing Detention Facility
Select driveway access to property: Existing Drive
Fire sprinklers? Yes
Setbacks Front 20'
Setback Side 1 15'
Setback Side 2 15'
Setback Rear 15'
Stories 2
Heated Area (Sqft) 37500
Total Area (Sqft) 37500
Total Estimated Cost 16100000.00
Building Height 30
Building Code Construction Type II
Building Code Element B
Building Code Occupancy Types Institutional
Dev Permit # F023-
Design Occupant Load 268
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# X20
Is this an addition for commercial or residential use? Commercial

Review Notes

8/24/2020 Application pending.
10/13/2020 Zoning Review - Reviewed
10/13/2020 Plan Review - Reviewed
10/23/2020 Permit Issued

Contractors

Name / Business License Title Role
William P Byrne
Ajax Building Company Llc
County License & State License & Liability Insurance & Workers Comp Expired.
CGC042112 Cert. General Contractor
Erik W Worthmann
Comfort Temp Company/dba Ct Mechanical
CMC1249305 Cert. Mechanical Subcontractor
Eric H Touchton
Touchton Plumbing Contractors Inc
County License & State License Expired.
CFC056489 Cert. Plumbing Subcontractor
Thomas Stalvey
Ace Electric Inc Of Valdosta Georgia
County License & State License & Liability Insurance & Workers Comp Expired.
EC0001433 Cert. Electrical Subcontractor
Ronald Benke
Cox Fire Protection Inc
County License & State License & Liability Insurance & Workers Comp Expired.
FPC12-000062 Cert. Fire/water System Subcontractor

Inspections

Inspection Notes Performed By Date
Passed: Electrical - Temporary Service Troy Crews 11/25/2020
Release to power company Troy Crews 11/25/2020
Passed: Building - Footer Partial Cell Foundations Troy Crews 1/21/2021
Passed: Engineering - Setbacks Troy Crews 1/21/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Waste Lines South Line Of Building Troy Crews 1/21/2021
Passed: Building - Footer South End And ,southeast Cell Footers Troy Crews 1/26/2021
Passed: Engineering - Setbacks Troy Crews 1/26/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Northwest Section Troy Crews 1/27/2021
Passed: Electrical - 1st Underground Rough–In Troy Crews 1/29/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 1/29/2021
Passed: Building - Footer 3 Column Pads East Side One 12 Ft. Two 5 Ft. Troy Crews 2/11/2021
Passed: Engineering - Setbacks Troy Crews 2/11/2021
Passed: Building - Footer 5x52ft. Deep Columns West Side Troy Crews 2/18/2021
Passed: Engineering - Setbacks Troy Crews 2/18/2021
Passed: Plumbing/Gas - 1st Underground Rough–In Tie In Of 2 Main Sewer Lines With 2 Way Clean Out Troy Crews 2/25/2021
Passed: Building - Footer 14 Ft. Pads And One 3x3 Pad Troy Crews 2/26/2021
Passed: Engineering - Setbacks Troy Crews 2/26/2021
Passed: Building - Monolithic Slab Troy Crews 3/5/2021
Passed: Engineering - Setbacks Troy Crews 3/5/2021
Passed: Building - Monolithic Slab Troy Crews 3/8/2021
Passed: Engineering - Setbacks Troy Crews 3/8/2021
Passed: Building - Slab Electric Room Troy Crews 3/29/2021
Passed: Building - Monolithic Slab Troy Crews 3/29/2021
Passed: Engineering - Setbacks Troy Crews 3/29/2021
Passed: Building - Masonry Wall Reinforcing Sw Corner North Of Electric Room Troy Crews 4/6/2021
Passed: Building - Masonry Wall Reinforcing South Side Of Connecting Corridor And N.w. Corner Troy Crews 4/8/2021
Passed: Building - Masonry Wall Reinforcing North Side Of Corridor And Various First Lift Block Cells Troy Crews 4/12/2021
Cancelled: Building - Masonry Wall Reinforcing Troy Crews 4/13/2021
Passed: Building - Framing Anchor Bolts At Red Iron Beams. Troy Crews 4/14/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 4/15/2021
Passed: Building - Monolithic Slab Condenser Slabs South And North Troy Crews 4/15/2021
Passed: Engineering - Setbacks Troy Crews 4/15/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 4/16/2021
Passed: Building - Masonry Wall Reinforcing Center Section Interior Walls First Lift And Partial Second Lift. Troy Crews 4/20/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 4/21/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 4/22/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 4/26/2021
Passed: Building - Masonry Wall Reinforcing Top Out Electric Room Area And Partial Interior Hallways Troy Crews 4/28/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 4/29/2021
Passed: Building - Framing Troy Crews 5/7/2021
Passed: Building - Slab Troy Crews 5/11/2021
Passed: Building - Slab Troy Crews 5/19/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 5/20/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 5/25/2021
Rescheduled 5/27/2021:Building - Masonry Wall Reinforcing Troy Crews 5/26/2021
Rescheduled 5/27/2021:Building - Framing Troy Crews 5/26/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 5/27/2021
Passed: Building - Framing Troy Crews 5/27/2021
Passed: Building - Slab Troy Crews 6/2/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/2/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/3/2021
Passed: Plumbing/Gas - 2nd Rough-In Hot Water Lines Pressure 100p.s.i. Troy Crews 6/3/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/4/2021
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 6/4/2021
Passed: Building - Lintel/Tie Beam Troy Crews 6/8/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/8/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/10/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/14/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/15/2021
Passed: Building - Lintel/Tie Beam Troy Crews 6/16/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/16/2021
Passed: Building - Framing Troy Crews 6/16/2021
Passed: Building - Fire Rated Wall Troy Crews 6/16/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/17/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/18/2021
Passed: Building - Rated Assembly Fastening Troy Crews 6/18/2021
Passed: Building - Lintel/Tie Beam Troy Crews 6/21/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/21/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/22/2021
Passed: Building - Fire Rated Wall Troy Crews 6/22/2021
Passed: Building - Lintel/Tie Beam Troy Crews 6/23/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/23/2021
Passed: Building - Rated Assembly Fastening Troy Crews 6/23/2021
Passed: Building - Fire Rated Wall Troy Crews 6/23/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/24/2021
Passed: Building - Ext Strapping/Wall Sheathing South Side Corridor Troy Crews 6/24/2021
Passed: Building - Rated Assembly Fastening Troy Crews 6/24/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 6/25/2021
Passed: Building - Rated Assembly Fastening Troy Crews 6/25/2021
Passed: Building - Fire Rated Wall Troy Crews 6/25/2021
Passed: Building - Lintel/Tie Beam Troy Crews 7/1/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 7/1/2021
Passed: Building - Rated Assembly Fastening Troy Crews 7/9/2021
Passed: Building - Fire Rated Wall Troy Crews 7/9/2021
Passed: Building - Wall Sheathing Troy Crews 7/12/2021
Passed: Building - Slab Pictures Received Troy Crews 7/21/2021
Passed: Building - Masonry Wall Reinforcing Pictures Received Troy Crews 7/21/2021
Passed: Building - Footer Pictures Received Troy Crews 7/22/2021
Passed: Engineering - Setbacks Troy Crews 7/22/2021
Passed: Building - Masonry Wall Reinforcing Pictures Received Troy Crews 7/22/2021
Passed: Building - Framing Troy Crews 7/29/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 7/29/2021
Passed: Building - Lintel/Tie Beam Troy Crews 7/30/2021
Passed: Building - Fire Rated Wall Troy Crews 8/4/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 8/5/2021
Passed: Building - Rated Assembly Fastening Troy Crews 8/5/2021
Cancelled: Mechanical - Rough In Troy Crews 8/10/2021
Passed: Building - Framing Troy Crews 8/11/2021
Passed: Building - Fire Rated Wall Troy Crews 8/11/2021
Passed: Mechanical - Rough In Pressure Test Anthony Aslan 8/11/2021
Passed: Building - Lintel/Tie Beam Troy Crews 8/16/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 8/16/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 8/17/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 8/18/2021
Passed: Mechanical - Rough In Pressure Test Anthony Aslan 8/18/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 8/19/2021
Passed: Building - Lintel/Tie Beam Troy Crews 8/23/2021
Passed: Building - Masonry Wall Reinforcing Make Sure #4 Bars Are Changed Out To #5 Troy Crews 8/23/2021
Passed: Building - Masonry Wall Reinforcing # 4 Bar Each Cell Troy Crews 8/24/2021
Passed: Building - Masonry Wall Reinforcing Also 2 Wings At Door Area Troy Crews 8/27/2021
Passed: Building - Slab Troy Crews 9/7/2021
Failed: Mechanical - Pipe Pressure Test Could Not Build Pressure, However Did Check Some Duct For Wrap Troy Crews 9/8/2021
Failed: Mechanical - Performance Test and Balance No Pressure Troy Crews 9/8/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 9/16/2021
Passed: Plumbing/Gas - Water Pipe Troy Crews 9/20/2021
Passed: Mechanical - Rough In Leak Test Smoke Anthony Aslan 9/20/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 9/22/2021
Passed: Building - Lintel/Tie Beam Troy Crews 9/27/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 9/27/2021
Passed: Building - Masonry Wall Reinforcing Troy Crews 9/29/2021
Passed: Mechanical - Pipe Pressure Test #5 Anthony Aslan 9/30/2021
Passed: Electrical - Permanent Power Troy Crews 10/1/2021
Release to power company Troy Crews 10/1/2021
Passed: Building - Footer Troy Crews 10/5/2021
Passed: Engineering - Setbacks Troy Crews 10/5/2021
Passed: Building - Framing Troy Crews 10/7/2021
Passed: Mechanical - Rough In Anthony Aslan 10/11/2021
Passed: Plumbing/Gas - 2nd Rough-In Gas Test On Line Anthony Aslan 10/12/2021
Passed: Building - Rated Assembly Fastening Troy Crews 10/12/2021
Passed: Mechanical - Pipe Pressure Test Anthony Aslan 10/14/2021
Passed: Building - Rated Assembly Fastening Troy Crews 10/15/2021
Passed: Electrical - Above Ceiling Troy Crews 10/20/2021
Passed: Mechanical - Rough In East Duct Anthony Aslan 10/21/2021
Passed: Building - Wall Sheathing Troy Crews 10/26/2021
Passed: Building - Wall Sheathing Troy Crews 10/27/2021
Passed: Mechanical - Rough In Troy Crews 11/1/2021
Passed: Mechanical - Rough In To Allow For Grid Ceiling Channel To Be Installed Anthony Aslan 11/5/2021
Passed: Fire - Operational Test - Sprinkler/Standpipe Pressure Test Of Overhead Sprinkler System. 4" Fdc Pipe Not Tested, Will Be Inspected/tested At A Later Date. Lance Hill 12/22/2021
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 1/7/2022
Passed: Electrical - Above Ceiling Troy Crews 1/25/2022
Passed: Building - Final Release Of C.o. Pending F.d. And Smoke Test Troy Crews 2/22/2022
Passed: Fire - Operational Test - Sprinkler/Standpipe Lance Hill 2/22/2022
Passed: Fire - Operational Test - Alarm System Lance Hill 2/22/2022
Failed: Fire - Fire Final Smoke Ejection System Not Operational Yet Lance Hill 2/23/2022
Cancelled: Fire - Operational Test - Sprinkler/Standpipe Completed 2/22/22 Lance Hill 2/23/2022
Cancelled: Fire - Operational Test - Alarm System Completed 2/22/22 Lance Hill 2/23/2022
Cancelled: Fire - Fire Final Rescheduled For A Later Date Lance Hill 2/23/2022
Passed: Fire - Operational Test - Sprinkler/Standpipe Completed And Passed Pressure Test Of Standpipe 12/30/21 Lance Hill 2/23/2022
Failed: Building - Final Control Dampers Not Operating Troy Crews 3/11/2022
Failed: Fire - Fire Final Control Dampers Not Operating Lance Hill 3/11/2022
Passed: Certificate-Release Certificate Troy Crews 3/15/2022
Passed: Building - Final Troy Crews 3/15/2022
Passed: Fire - Fire Final Lance Hill 3/15/2022

Documents

File Name Date File Size
Documentation 20200506 102246.pdf 2025.07.04 1.94MB
Certificate Of Mh Occupancy.pdf 2020.04.14 225.19kB

Contact Us

Building Department

Office Hours

Monday-Friday
8:00 A.M. - 4:30 P.M.

Contact Information

Phone: 386-758-1008
Fax: 386-758-2160

Email: bldginfo@columbiacountyfla.com

Location

135 NE Hernando Ave.
Lake City, FL 32055 (opens in new window)

Mailing Address

P.O. Box 1529
Lake City, FL 32056-1529

Public Records

Public records policy and fees

Board of County Commissioners
Tel. (386) 758-1326
Fax: (386) 758-2182
Email: publicrecords@columbiacountyfla.com

Mailing Address:
P.O. Box 1529
Lake City, FL 32056-1529

Citizen Feedback

Let us know how we're doing

ADA Accessibility

Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the Columbia County ADA Coordinator at (386) 758-3344. You may also email that office at hr@columbiacountyfla.com and provide a brief description of the inaccessible feature.

Columbia County strives to provide reasonable accommodations to help people with disabilities have an equal opportunity to participate in our public meetings. Please notify our ADA Coordinator at least 48 hours prior to the public meeting by calling (386) 758-3344.