| Passed: Building - Footer |
|
Troy Crews |
10/26/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
10/26/2020 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
10/26/2020 |
| Release to power company |
|
Troy Crews |
10/26/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
11/2/2020 |
| Rescheduled 11/4/2020:Building - Slab |
|
Melissa Garber |
11/3/2020 |
| Passed: Building - Slab |
|
Troy Crews |
11/4/2020 |
| Passed: Building - Roof Decking |
|
Troy Crews |
11/25/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Done On 11-25 With Walls |
Troy Crews |
12/1/2020 |
| Passed: Building - Wall Sheathing |
Done 11-25 With Roof |
Troy Crews |
12/1/2020 |
| Passed: Building - Framing |
|
Troy Crews |
12/16/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
12/16/2020 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
12/16/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/16/2020 |
| Passed: Building - Insulation |
Need To Separate Bath Fans Or Upsize Duct After Tee |
Troy Crews |
12/18/2020 |
| Passed: Electrical - Permanent Power |
Need Picture Of Under Ground Pipe Before Release. Also Need Septic Release |
Anthony Aslan |
1/27/2021 |
| Release to power company |
Rec'd Pictures |
|
2/1/2021 |
| Passed: Building - Final |
Need Septic Release & Blower Door Test Results |
Anthony Aslan |
2/10/2021 |
| Septic Release Inspection |
Need Blower Door Test Results |
Health Dept |
3/18/2021 |
| Certificate-Release Certificate |
Rec'vd Documents |
Anthony Aslan |
3/30/2021 |