| Passed: Building - Footer |
|
Matt Forsyth |
12/8/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
12/8/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
1/4/2021 |
| Passed: Building - Slab |
|
Troy Crews |
1/19/2021 |
| Passed: Building - Masonry Wall Reinforcing |
|
Matt Forsyth |
2/23/2021 |
| Passed: Building - Vertical Cells/Columns |
|
Matt Forsyth |
2/23/2021 |
| Passed: Building - Lintel/Tie Beam |
|
Troy Crews |
3/25/2021 |
| Passed: Building - Roof Decking |
|
Troy Crews |
6/11/2021 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
6/11/2021 |
| Cancelled: Building - Framing |
|
Troy Crews |
7/29/2021 |
| Passed: Building - Framing |
|
Troy Crews |
8/3/2021 |
| Passed: Electrical - 2nd Rough-In |
Partial On Porch Areas Outside For Stucco |
Troy Crews |
10/19/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/25/2022 |
| Failed: Plumbing/Gas - 2nd Rough-In |
Need Pressure On Water And Gas Lines. |
Troy Crews |
1/25/2022 |
| Passed: Building - Insulation |
|
Troy Crews |
2/4/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Pressure Added |
Troy Crews |
2/4/2022 |
| Failed: Mechanical - Rough In |
Dryer Duct Termination And Oven Hood ? |
Troy Crews |
2/21/2022 |
| Passed: Mechanical - Rough In |
Ducts Connected |
Troy Crews |
2/24/2022 |
| Septic Release Inspection |
|
Health Dept |
4/27/2022 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
7/20/2022 |
| Release to power company |
|
Troy Crews |
7/20/2022 |
| Passed: Building - Final |
|
Troy Crews |
12/14/2022 |