Additions
Permit
| Application #: | 47127 |
| Permit #: |
000040473 |
| Related Permit: |
|
| Submitted: | |
| Issued: | Monday, August 31, 2020 |
| Expires: | Tuesday, June 1, 2021 |
| Completed: | Tuesday, June 1, 2021 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Elevation regulation |
Existing Building |
| Finished floor requirement |
Meet existing structure |
| Fema map number |
12023C0383D |
| In floodway |
N |
| Is this an addition for commercial or residential use? |
Residential |
| Description of addition: |
garage, living area, porch |
| Total Estimated Cost |
60000 |
| Heated Area (Sqft) |
1957 |
| Total Area (Sqft) |
3560 |
| Stories |
1 |
| Building Height |
16 |
| Select driveway access to property: |
Existing Drive |
| Fire sprinklers? |
No |
| Building Code Construction Type |
V |
| Building Code Occupancy Types |
Residential |
| Building Code Element |
B |
| Occupancy Use Title |
single family |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setback Side 2 |
25' |
| Setback Rear |
25' |
| Septic# |
20-0679 |
| Dev Permit # |
F023- |
| Building Code Edition |
Florida Building Code 2017 6th Edition & 2014 National Electrical Code |
Review Notes
| 8/24/2020 |
Application Converted |
| 8/24/2020 |
Point Review - Received-Hard Copy Application |
| 8/24/2020 |
Point Review - Reviewed |
| 8/25/2020 |
Zoning Review - Reviewed |
| 8/27/2020 |
Plan Review - Documents Required |
| 8/28/2020 |
Plan Review - Reviewed |
| 8/31/2020 |
Zoning Review - Reviewed |
| 8/31/2020 |
Permit Issued |
Contractors
| Name / Business |
License |
Title |
Role |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Failed: Plumbing/Gas - 1st Underground Rough–In |
Not Ready |
Troy Crews |
9/9/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/9/2020 |
| Failed: Building - Footer |
Not Ready |
Troy Crews |
9/9/2020 |
| Failed: Building - Monolithic Slab |
Not Read |
Troy Crews |
9/9/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/9/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
9/10/2020 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
9/14/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/14/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Partial |
Troy Crews |
10/5/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
10/12/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
10/26/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
10/30/2020 |
| Passed: Building - Framing |
|
Troy Crews |
11/30/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/11/2021 |
| Passed: Electrical - Above Ceiling |
|
Troy Crews |
1/11/2021 |
| Cancelled: Electrical - 2nd Rough-In |
|
Troy Crews |
1/13/2021 |
| Cancelled: Electrical - Above Ceiling |
|
Troy Crews |
1/13/2021 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
1/13/2021 |
| Release to power company |
|
Troy Crews |
1/13/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
2/22/2021 |
| Septic Release Inspection |
|
Health Dept |
4/16/2021 |
| Passed: Building - Final |
|
Troy Crews |
6/1/2021 |