| Release to power company |
Sent To Wrong Power Comp. |
Matt Forsyth |
9/8/2020 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
9/8/2020 |
| Release to power company |
|
Matt Forsyth |
9/8/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
9/10/2020 |
| Passed: Building - Monolithic Slab |
|
Matt Forsyth |
9/16/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
9/16/2020 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
9/28/2020 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/28/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
10/7/2020 |
| Failed: Mechanical - Rough In |
Not Finished |
Matt Forsyth |
10/7/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
10/7/2020 |
| Passed: Building - Framing |
|
Matt Forsyth |
10/7/2020 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
10/8/2020 |
| Passed: Building - Insulation |
|
Matt Forsyth |
10/14/2020 |
| Passed: Electrical - Permanent Power |
Need Septic Release To Release Permanent Power |
Matt Forsyth |
11/12/2020 |
| Release to power company |
|
Melissa Garber |
11/16/2020 |
| Septic Release Inspection |
|
Health Dept |
11/16/2020 |
| Cancelled: Electrical - Permanent Power |
|
Matt Forsyth |
12/8/2020 |
| Failed: Building - Final |
Need Blower Door Test, Final Termite Treatment Water Heater Overflow Pipe To Outside |
Matt Forsyth |
12/8/2020 |
| Passed: Building - Final |
|
Matt Forsyth |
12/10/2020 |