| Septic Release Inspection |
|
Health Dept |
7/22/2020 |
| Cancelled: Building - Footer |
|
Matt Forsyth |
7/30/2020 |
| Cancelled: Engineering - Setbacks |
|
Matt Forsyth |
7/30/2020 |
| Passed: Building - Monolithic Slab |
|
Matt Forsyth |
7/30/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
7/30/2020 |
| Passed: Building - Monolithic Slab |
|
Matt Forsyth |
8/18/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/18/2020 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
8/28/2020 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
8/28/2020 |
| Cancelled: Building - Framing |
|
Matt Forsyth |
8/28/2020 |
| Passed: Building - Framing |
|
Matt Forsyth |
9/24/2020 |
| Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
9/24/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
9/24/2020 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
9/24/2020 |
| Release to power company |
|
Matt Forsyth |
9/24/2020 |
| Passed: Building - Final |
|
Matt Forsyth |
12/10/2020 |