| Passed: Building - Footer |
Need Permit Posted On Site |
Matt Forsyth |
7/23/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
7/23/2020 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
8/5/2020 |
| Release to power company |
|
Matt Forsyth |
8/5/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
8/7/2020 |
| Passed: Building - Slab |
|
Matt Forsyth |
8/13/2020 |
| Passed: Building - Roof Decking |
|
Troy Crews |
9/1/2020 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
9/1/2020 |
| Passed: Building - Framing |
|
Matt Forsyth |
9/17/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
9/17/2020 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
9/17/2020 |
| Failed: Plumbing/Gas - 2nd Rough-In |
Vent Pipe Not Complete In Two Places |
Matt Forsyth |
9/17/2020 |
| Passed: Building - Strapping |
|
Matt Forsyth |
9/17/2020 |
| Passed: Building - Insulation |
|
Matt Forsyth |
9/24/2020 |
| Septic Release Inspection |
|
Health Dept |
12/2/2020 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
12/17/2020 |
| Release to power company |
|
Matt Forsyth |
12/17/2020 |
| Passed: Building - Final |
|
Matt Forsyth |
1/8/2021 |