Permit Details

Permit Search

Permit

New Residential Construction

894 SE GABE ST
LAKE CITY, FL 32025

Permit #
000039946
Application #
46226
Status Completed
  1. Submitted —
  2. Issued Jun 15, 2020
  3. Expires Dec 5, 2021
  4. Completed Jun 10, 2021

Property

Parcel #
09205-004
Owner
Stalvey Brandon R
Acres
58.35
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0405C
This is the construction of a
Single Family Dwelling
Stories
1
Heated Area (Sqft)
2370
Total Area (Sqft)
3685
Building Height
23
Septic# (00-0000) or (X00-000)
20-0395
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code

Status & Review History

  1. Application pending.
  2. Point Review - Processing
  3. Zoning Review - On Hold-Incomplete
  4. Zoning Review - Email Sent
  5. Plan Review - Documents Required
  6. Plan Review - Reviewed
  7. Final Review - Documents Required
  8. Permit Issued

Contractors

  • Isaiah Cully

    Ic Construction Llc

    License
    CBC1259655
    Title
    Building Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Tyler M Turner

    Tmt Roofing Llc

    License
    CCC1330410
    Title
    Cert Roofing
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor

Inspections

  1. Aug 5, 2020

    Passed: Electrical - Temporary Service

    No Structural Inspections Until Noc Is Received

    Inspected by Troy Crews

  2. Aug 5, 2020

    Release to power company

    Inspected by Troy Crews

  3. Sep 4, 2020

    Passed: Building - Footer

    Reminder Install Ground Wire On Footer Steel

    Inspected by Troy Crews

  4. Sep 4, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Sep 23, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Sep 28, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Oct 28, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Oct 28, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  9. Dec 2, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Dec 2, 2020

    Failed: Plumbing/Gas - 2nd Rough-In

    Pressure Lost On Water Lines

    Inspected by Troy Crews

  11. Dec 2, 2020

    Failed: Building - Framing

    T-08 Truss Needs Additional Strapping

    Inspected by Troy Crews

  12. Dec 2, 2020

    Failed: Mechanical - Rough In

    Exhaust Duct For Oven Must Have Smooth Interior , Questions About Approved Tape For Duct Connections, Access To Fresh Air Motor ? Will Send E-mail Need To Meet Duct Insatllers Onsite. Aslo Need Strapping On Bath Fan Ducts.

    Inspected by Troy Crews

  13. Jan 20, 2021

    Failed: Plumbing/Gas - 2nd Rough-In

    Pressure Lost On Water Lines

    Inspected by Troy Crews

  14. Jan 20, 2021

    Passed: Building - Framing

    Truss Corrected

    Inspected by Troy Crews

  15. Jan 20, 2021

    Passed: Mechanical - Rough In

    Items Corrected

    Inspected by Troy Crews

  16. Jan 21, 2021

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  17. Apr 23, 2021

    Passed: Electrical - Permanent Power

    Need Septic Final

    Inspected by Troy Crews

  18. May 4, 2021

    Septic Release Inspection

    Need Final Driveway Release

    Inspected by Health Dept

  19. May 5, 2021

    Release to power company

    Inspected by Melissa Garber

  20. Jun 8, 2021

    Passed: Building - Final

    Release Pending Letter From Owner Regarding Water Heater L.p. Connection

    Inspected by Troy Crews

  21. Jun 10, 2021

    Certificate-Release Certificate

    Inspected by Troy Crews

Documents