Permit Details

Permit Search

Permit

Storage Building

1483 SW LEGION DR
LAKE CITY, FL 32024

Permit #
000039926
Application #
46034
Status Completed
  1. Submitted —
  2. Issued Jun 11, 2020
  3. Expires Sep 14, 2021
  4. Completed Mar 18, 2021

Property

Parcel #
03051-203
Owner
Wilson Brenda Brucks
Acres
5.01
Subdivision
Legion Place
Zoning
A-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
NONE Non-Habitable Structure
Fema map number
12023C0290D
Type of Structure
Garage
Commercial or Residential?
Residential
Total Area (Sqft)
1040
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Storage
Occupancy Use Title
garage
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setback Rear
10 ACCESSORY STRUCTURE
Septic# (00-0000) or (X00-000)
20-0425
Dev Permit #
F023-
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code

Status & Review History

  1. Application pending.
  2. Application Converted
  3. Point Review - On Hold
  4. Point Review - Documents Required
  5. Point Review - Corrections Needed
  6. Point Review - Corrections Needed
  7. Point Review - On Hold-Incomplete
  8. Zoning Review - Reviewed
  9. Point Review - Received
  10. Plan Review - Reviewed
  11. Final Review - Documents Required
  12. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Jun 9, 2020

    Septic Release Inspection

    Inspected by Health Dept

  2. Jun 19, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  3. Jun 19, 2020

    Failed: Building - Framing

    Need Letter On Beam Change

    Inspected by Matt Forsyth

  4. Jun 19, 2020

    Failed: Building - Lintel/Tie Beam

    Need. Letter On Changes

    Inspected by Matt Forsyth

  5. Jun 19, 2020

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  6. Jun 19, 2020

    Passed: Building - Wall Sheathing

    Inspected by Matt Forsyth

  7. Jun 19, 2020

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Matt Forsyth

  8. Jun 19, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  9. Aug 6, 2020

    Passed: Building - Lintel/Tie Beam

    Letter Received

    Inspected by Matt Forsyth

  10. Aug 6, 2020

    Passed: Building - Framing

    Letter Received

    Inspected by Matt Forsyth

  11. Mar 18, 2021

    Passed: Building - Final

    Inspected by Matt Forsyth