| Passed: Building - Footer |
|
Troy Crews |
5/27/2020 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
5/27/2020 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
5/27/2020 |
| Release to power company |
|
Troy Crews |
5/27/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
6/10/2020 |
| Passed: Building - Slab |
|
Troy Crews |
6/17/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
7/16/2020 |
| Passed: Building - Framing |
|
Troy Crews |
7/16/2020 |
| Passed: Building - Roof Decking |
|
Troy Crews |
7/16/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
7/28/2020 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
7/28/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
7/28/2020 |
| Passed: Building - Insulation |
|
Troy Crews |
8/5/2020 |
| Passed: Electrical - Permanent Power |
Need Final Septic- Rec'd
assessments Owed Prior To Final |
Troy Crews |
10/1/2020 |
| Release to power company |
|
Melissa Garber |
10/7/2020 |
| Septic Release Inspection |
Power To Be Released When Waiver Is Approved |
Health Dept |
10/7/2020 |
| Failed: Building - Final |
Need Locking Caps On Condenser Service Plugs, Seal All Ductwork At Air Handler Including Back Side Of Return And Unit. |
Troy Crews |
11/24/2020 |
| Failed: Building - Final |
Need To Seal Back Of Supply And Return Ducts.
|
Anthony Aslan |
11/30/2020 |
| Passed: Building - Final |
Duct Sealed On Interior Per Contractor |
Troy Crews |
12/16/2020 |