| Passed: Building - Footer |
|
Matt Forsyth |
4/24/2020 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/24/2020 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
5/8/2020 |
| Passed: Building - Slab |
|
Matt Forsyth |
5/15/2020 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
6/16/2020 |
| Failed: Plumbing/Gas - 2nd Rough-In |
No Permit On Site Permit Box Is Empty No Full Working Set Of Drawings |
Matt Forsyth |
7/1/2020 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
7/7/2020 |
| Passed: Building - Framing |
|
Matt Forsyth |
7/7/2020 |
| Passed: Building - Strapping |
|
Matt Forsyth |
7/7/2020 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
7/7/2020 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
7/7/2020 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
7/17/2020 |
| Passed: Building - Insulation |
|
Matt Forsyth |
8/3/2020 |
| Failed: Electrical - Permanent Power |
Need Septic Release And Driveway Also There's A Couple Of Loose Wires(electrical ) Needing Wire Nuts |
Matt Forsyth |
12/8/2020 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
1/25/2021 |
| Release to power company |
|
Melissa Garber |
1/26/2021 |
| Septic Release Inspection |
|
Health Dept |
1/26/2021 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
1/26/2021 |
| Release to power company |
|
Matt Forsyth |
1/26/2021 |
| Passed: Building - Final |
|
Matt Forsyth |
5/21/2021 |